Construction Updates
Construction updates as seen on 25th October 2021
Construction Status
Jan 2022 Possession 81.09%
Progress:81.09%
Stage:
Wet area wall tile work and water proofing from Ground to 7th Floor completed.
Wet area floor tiling from Ground to 7th Floor completed.
Dry tiling from Ground to 7th Floor completed.
1st coat painting work from Ground to 7th Floor completed.
Wardrobe installation from Ground to 5th Floor completed.
Kitchen cabinet installation from Ground to 5th Floor completed.
Timber door installation from Ground to 5th Floor completed.
Vanity counter installation from Ground to 2nd Floor completed.
MEP 1st and 2nd Fix work from Ground to Roof level completed.
False ceiling work from Ground to 4th Floor completed.
Balcony handrail installation from Podium to 3rd Floor completed.
90% of external plastering work completed.
85% of aluminium & glazing work completed.
80% of stone cladding work completed.
55% of lift installation completed.
55% of boundary wall completed.
Launched:15th January 2020
Planned Handover:January 2022
Progress:76.7%
Stage:
Plaster work for all floors completed.
Wet area wall tile work from 1st to 6th floor completed.
80% of wet area wall tile at 7th floor completed.
Wet area water proofing from 1st to 7th floor completed.
Wet area floor tiling from Ground to 7th floor completed.
95% of dry tiling from Ground to 4th floor completed.
90% of dry tiling on 5th & 6th floor completed.
Painting work from Ground to 7th floor under progress.
100% of wardrobe fixing on Ground & Podium floor completed.
90% of Kitchen cabinet work on Ground & Podium floor completed.
100% of Doors work on Ground & Podium floor completed.
100% of Vanity work on Ground & Podium floor completed.
MEP first fix work from 1st to 7th floor and Roof completed.
Façade work – External plastering under progress.
Façade work – Aluminum & glazing under progress.
Façade work – Stone cladding under progress.
Façade work – Painting under progress.
100% of Garbage chute work completed.
Lift work under progress.
Window cleaning system work under progress.
Launched:15th January 2020
Planned Handover:January 2022
Progress:66%
Stage:
Plaster work at 5th & 6th Floor completed.
Wet area wall tile work from 1st to 6th Floor completed.
Wet area floor tiling from Ground Floor to 3rd Floor completed.
Dry tiling from Ground Floor to 4th Floor completed.
Painting work from Ground Floor to 7th Floor under progress.
100% of Wardrobe work at Ground and Podium Floor completed.
100% of Doors work at Ground Podium Floor completed.
100% of Vanity work at Ground and Podium Floor completed.
MEP 1st Fix work from 1st to 7th Floor and Roof completed.
False Ceiling work from Ground to 3rd Floor under progress.
Façade work – External plastering work under progress.
Façade work – Aluminum & Glazing work under progress.
Launched:15th January 2020
Planned Handover:January 2022
Progress:51%
Stage:
Casting of parapet wall completed.
Block work at Seventh and Roof floor completed.
Plaster work from Podium to 4th floor completed.
Wet area water proofing from 1st to 3rd floor completed.
Wet area floor and wall tiling from Ground floor to 3rd floor under progress.
MEP 1st Fix works from 1st to 3rd floor completed.
Facade external plastering works under progress.
Launched:15th January 2020
Planned Handover:January 2022
Progress:45%
Stage:
Roof Floor and Top of Roof Slab casting completed.
Parapet wall work under progress.
Block work on Second, Third and Fourth Floor completed.
Block work from Fifth to Seventh Floor under progress.
Plaster work at Podium, First and Second Floor completed.
Wet area water proofing from Ground to Second Floor under progress.
Wet area wall and floor tiling from Ground to Third Floor under progress.
Dry tiling from Ground to Second Floor under progress.
MEP 1st fix works at First Floor and Second Floor completed.
MEP 2nd fix works from Ground to Fourth Floor under progress.
Launched:15th January 2020
Planned Handover:January 2022
Progress:42%
Stage:
Sixth Floor to Roof all the vertical elements completed.
Seventh Floor slab casting completed.
Block work at Ground Floor, Podium Floor and First Floor completed.
Block work at Second Floor, Third Floor and Fourth Floor under progress.
MEP 1st fix work at Ground and Podium Floor completed.
MEP 1st fix work at First and Second Floor under progress.
MEP 2nd fix work at Ground Floor, Podium Floor and First Floor under progress.
Launched:15th January 2020
Planned Handover:January 2022
Progress:33.78%
Stage:
Fifth Floor slab casting completed.
Third to Sixth Floor all the vertical elements completed.
Block work at Ground Floor completed.
Block work at Podium Floor and First Floor under progress.
MEP works under progress at Ground Floor and Podium Floor.
Launched:15th January 2020
Planned Handover:January 2022
Progress:28.49%
Stage:
2nd and 3rd floor slabs concreted.
Block work in progress at Ground & Podium Floor.
Plastering work in progress at Ground Floor.
1st floor to 4th floor – all vertical elements concreted.
Launched:15th January 2020
Planned Handover:January 2022
Progress:24.19%
Stage:
1st floor slab completed.
1st floor to 2nd floor Column / Walls – 50% completed.
Launched:15th January 2020
Planned Handover:January 2022
Progress:22.04%
Stage:
Casting of Podium floor completed.
50% C asting of 1st floor completed.
Duplex Area – Cover slab concreted.
Launched:15th January 2020
Planned Handover:January 2022
Progress:14.05%
Stage:
Casting of Grade slab completed.
Casting of Ramp to Podium floor completed.
Ground Floor – Column / Walls concreting completed.
Launched:15th January 2020
Planned Handover:January 2022
Progress:12.71%
Stage:
Underground services for Drainage completed.
Back Filling below the Grade slab completed.
Grade slab in progress.
Launched:15th January 2020
Planned Handover:January 2022
Progress:9.82%
Stage:
All the Foundations concreted.
Neck Column & Tie beam works completed.
Substructure waterproofing completed.
Backfilling up to Tie beam level completed.
Launched:15th January 2020
Planned Handover:January 2022


Progress:2.25%
Stage:
Excavation completed.
Casting of major areas – Raft & Foundations completed.
Launched:15th January 2020
Planned Handover:January 2022
Progress:0.08%
Stage:
Mobilization completed
Excavation in progress
Launched:15th January 2020
Planned Handover:January 2022

This project is registered under RERA project number: 2255