ZāZEN IVY – Construction Update

Al Furjan

16.45%

It is currently under construction and due for completion in March 2026.

This project is registered under RERA project number 3109.

Timeline

Progress:

16.45%

Stage:

Main Raft & Foundation:

Raft & isolated footing casting, 100% completed.
Casting of Tie beams, 95% completed.
Road base & Screed under Grade Slab (SOG), 80% completed.
MEP services under SOG, 60% completed.
Ground floor columns and core walls, 60% completed.
1st floor slab shuttering, 40% completed.
Tower Crane Setup and Operations, 100% completed.

Launched: 15th July 2024
Planned Handover: 30th March 2026

Progress:

13.49%

Stage:

Main Raft & Foundation:

2nd phase Waterproofing for Main Raft top, Zone 1, 100% completed.
2 layers of Back Filling & Solid Block for Substructure, Zone 1, 100% completed.
Casting Slab of Water Tank, Pump Rooms and Staircase, Zone 1, 100% completed.
Water Proofing Slab of Water Tank, Pump Rooms, Zone 1, 100% completed.
Casting Tie Beam and Water Proofing, Zone 1, 75% completed.
Road Base & Screed under Grade Slab, Zone 1, 25% completed.
MEP services under Grade Slab, Zone 1, 60% completed.
Excavation of Isolated footing, Road base & PCC, Zone 2, 75% completed.
Casting Isolated footing & Neck Columns, Zone 2, 50% completed.
Waterproofing Isolated footing & Neck Columns, Zone 2, 45% completed.
Casting Tower Crane Foundation, Zone 2, 100% completed.

Launched: 15th July 2024
Planned Handover: 30th March 2026

Progress:

9.12%

Stage:

Main Raft:

Reinforcement for main raft, lift pit and substation completed.
Main Raft concrete casting completed.
2nd phase Waterproofing for main raft top preparation 10% completed.

Under Ground Raft Works:

1st phase Waterproofing for raft (above PCC) and retaining walls completed.
Raft Reinforcement for UG Pump room and Water Tank (WT) completed.
UG raft and vertical elements for WT and pump room casting completed.
External waterproofing for WT walls 20% completed.

Launched: 15th July 2024
Planned Handover: 30th March 2026

Progress:

4.32%

Stage:

Main Raft:

1st Phase Of Waterproofing For Main Raft (Above PCC) Completed.
1st Phase Waterproofing Protection Screed Casted.
Reinforcement For Main Raft Lift Pit 80% Completed.

Under Ground Raft Works:
Excavation, Levelling, Compaction For U/G Water Tank And Pump Room Raft Completed.
Solid Blockwork Shuttering For Raft And Retaining Walls Completed.
Dewatering System Installation Completed. Dewatering Process Ongoing.
1st Phase Waterproofing For Raft (Above PCC) And Retaining Walls 50% Completed.
Launched: 15th July 2024
Planned Handover: 30th March 2026

Progress:

3.00%

Stage:

Water Tank and Pump Room: Zone 1 Excavation Completed.

Under Ground Raft Works:

Excavation completed including lift pits/LV rooms to required levels.
Compaction testing completed.
3 layers road base compaction and testing completed.
Raft foundation PCC blinging concrete casting completed.
Lift pit/LV room Raft Shuttering Works completed.
Water Proofing Preliminarily Works completed.

Launched:

15th July 2024

Planned Handover:

30th March 2026