ZāZEN Gardens – Construction Update

Al Furjan

65.52%

It is currently under construction and due for completion on 30th April 2024.

This project is registered under RERA project number 2474.

Timeline

Progress:

65.52%

Stage:

Pump Room: Installation of Equipment in Progress & MEP 3rd Fix in Progress.

Ground Floor: 100% of Block Work, Ceiling & Corridor Plaster Completed. MEP 2nd Fix Works in Progress. Installation of Generator Completed.

LV Room: MEP 2nd Fix Works in Progress.

1st Floor: Wall & Ceiling Painting, Balcony Upstand, False Ceiling Works all in Progress.

1st Floor: Wall & Ceiling Painting, Tiling Works, Kitchen Cabinet Works, MEP 2nd Fix in Progress. 100% of Block Works at Gym & Lounge Completed. Swimming Pool Works in Progress.

2nd Floor: Wall & Ceiling Painting, Balcony & Corridor Tiling, Vanity Counter Works, Kitchen Cabinet Works, Sanitary Ware installation,  MEP 2nd & 3rd Fix all in Progress.

3rd & 4th Floor: Wall & Ceiling Painting, Balcony & Corridor Tiling, Aluminium & Glazing Works, Sanitary Ware installation, MEP 2nd & 3rd Fix all in Progress.

5th & 6th Floor: Wall & Ceiling Painting, Aluminium & Glazing Works, Balcony and Corridor Tiling Works, False Ceiling Works, MEP 2nd & 3rd Fix all in Progress.

Roof Floor: Roof Water Proofing Completed. Erection of Steel Structure Works for Solar in Progress. MEP 2nd Fix Works in Progress.

Façade: External Painting for Façade (1st Floor to Roof Floor) in Progress. Ground Floor Aluminium Screens / Louvers in Progress.

Launched:

10th October 2022

Planned Handover:

30th April 2024

Progress: 58.32%
Stage:
Pump Room: Staircase Surface Epoxy Completed. Primer, Stucco & MEP 3rd Fix in Progress.
Ground Floor: 90% of Ceiling & Corridor Plaster Completed. Service Room MEP Works & Installation of Generator in Progress.
LV Room: MEP 2nd Fix Works in Progress.
1st Floor: Wall & Ceiling Painting, Balcony Upstand, False Ceiling Works all in Progress.
1st Floor: 100% Erection of Steel Structure for Gym Completed. 60% of Block Works at Gym & Lounge in Progress. Aluminium & Glazing Works in Progress.
2nd Floor: Wall & Ceiling Painting, Balcony Upstand, False Ceiling Works, Kitchen Cabinet Works all in Progress.
3rd & 4th Floor: MEP 2nd Fix for Apartments Completed.  False Ceiling Works in Progress. MEP 3rd Fix Completed.
5th Floor: 100% of Internal Plastering & Corridor Plastering Completed. MEP 2nd Fix  & False Ceiling Under Progress.
6th Floor: 100% of Plastering Works Completed. Tiling Works in Dry Area and Wet Area in Progress. 100% of Corridor Plaster Completed.
Façade: External Plaster Ground Floor to 1st Floor & Façade Completed. Ground Floor Aluminium Screens / Louvers in Progress.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 52.23%
Stage:
Pump Room: Installation of Equipment in Progress.
Ground Floor: 99% of Block Work Completed. 70% of Tiling Work Completed. MEP 2nd Fix Under Progress.
Substation: DEWA Authority approval obtained.
1st Floor: MEP 2nd Fix for Apartments Under Progress.
1st Floor: Installation of Sanitary Ware in Progress.
2nd Floor: MEP 2nd Fix for Apartments Under Progress. Balcony Tiling in Progress.
3rd & 4th Floor: MEP 2nd Fix for Apartments Under Progress. Plastering Works Completed.
5th Floor: 90% of Plastering, Wall & Ceiling Painting & Balcony Plaster Completed.
6th Floor: Block Work Completed. 30% of Ceiling Preparation Completed. MEP 1st Fix Completed.
Façade: External Plaster & Painting for Façade in Progress.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 47.50%
Stage:
Pump Room: Foundation Completed. Installation of Equipment in Progress.
Ground Floor: 90% of Block Work Completed. 80% of Ceiling Painting/Plaster Completed.
Substation: Work Completed. DEWA Authority Inspection for Substation applied.
1st Floor: Plastering Completed. Wall & Ceiling Painting in Progress.
1st Floor: Tiling Works, False Ceiling Work, Upstand for Balconies & Partition works in Progress.
3rd & 4th Floor: Plastering, Wall & Ceiling Painting, Tiling in Wet Area, Upstand & MEP 2nd Fix works in Progress.
5th Floor: Plastering, Wall & Ceiling Painting & MEP 2nd Fix works in Progress.
6th Floor: MEP 1st Fix & 2nd Fix work in Progress.
Façade: External Plaster Ground Floor to 1st Floor Completed. External Plaster for Façade in Progress.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 41.49%
Stage:
Ground Floor: Plant Room Plastering Completed.
Ground Floor: MEP 2nd Fix in Progress (Electrical, Plumbing, Fire Fighting and HVAC).
Substation: Plaster Preparation Completed. Painting in Progress.
1st Floor: Block Work & MEP 1st Fix Works Completed.
1st Floor: Plastering & MEP 2nd Fix Works in Progress.
2nd Floor: Plastering & MEP 1st Fix Works in Progress.
3rd & 4th Floor: Block Work Completed. MEP 1st Fix Works in Progress.
5th Floor: 75% of Block Work Completed.
6th Floor: 60% of Block Work Completed.
Roof Floor: De-Shuttering of Roof at Pour 02 Completed.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 38.25%
Stage:
Ground Floor: Block Work and Ceiling Painting/Plaster in Progress.
Ground Floor: MEP 1st Fix Completed, 2nd Fix in Progress.
Substation: Block Work and MEP 1st Fix Works Completed.
1st Floor: 95% of Block Work Completed.
1st Floor: MEP 1st & 2nd Fix Works in Progress.
2nd Floor: 97% of Block Work Completed. MEP 1st Fix Works Under Progress.
3rd & 4th Floor: 75% of Block Work Completed.
5th Floor: De-Shuttering of 5th Floor, Pour 01 & 02 Completed. 20% of Block Work Completed.
6th Floor: Casting of 6th Floor Slab Pour 01 & 02 Completed. 15% of Block Work Completed.
Roof Floor: Casting of Slab 02 Completed. 15% of Block Work Completed. De-Shuttering in Progress.
Swimming Pool: Structural Works and Plaster for Swimming Pool Completed.
Facade: External Plaster from Ground to 1st Floor Completed.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 31.35%
Stage:
Ground Floor: Plaster Preparation and Plaster for Lobby and Staircase Completed.
Ground Floor: Block Work, Ceiling Painting and Plaster Works in Progress.
Substation: Casting of Trench Completed and Block Work in Progress.
1st Floor: De-Shuttering of 1st Floor Slab at Pour 03 Completed.
1st to 3rd Floor: Block Work in Progress.
4th Floor: Casting of 4th Floor Slab Pour 02 Completed. Block Work in Progress.
4th Floor: De-Shuttering of 4th Floor Slab Pour 01 & 02 Completed.
5th Floor: Casting and Vertical Works at 5th Floor Slab Pour 02 Completed.
6th Floor: Casting of Verticals and Floor Slab at 6th Floor Pour 01 & 02 Completed.
Roof Floor: Casting of Verticals and Floor Slab at Roof Pour 01 Completed and Pour 02 in Progress.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 23.22%
Stage:
Underground: Tank Cleaning and Preparation of Tanks are in Progress.
Underground: Pump Room Plaster Preparation Completed and MEP 1st Fix Works in Progress.
1st Floor: Casting of 1st Floor Slab Pour 03 Completed.
1st Floor: De-Shuttering of 1st Floor Slab at Pour 01 & 02 Completed.
1st Floor: Stressing & Patching for 1st Floor at Pour 01, 02 & 03 Completed.
2nd Floor: Casting and De-Shuttering of 2nd Floor Slab Pour 02 Completed.
3rd Floor: Casting and De-Shuttering of 3rd Floor Slab Pour 01 & 02 Completed.
4th Floor: Casting of 4th Floor Slab Pour 01 Completed. Pour 02 is Partially Completed.
4th Floor: Stressing & Patching for 4th Floor at Pour 01 Completed and Pour 02 in Progress.
5th Floor: Casting of 5th Floor Slab Pour 01 Completed. Vertical Works at 5th Floor Pour 02 in Progress.
6th Floor: Casting of Verticals at 6th Floor Slab Pour 01 in Progress. Scaffolding & Shuttering Works at 6th Floor at Pour 01 in Progress.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 16.22%
Stage:
Sub Structure: Water Proofing for Exposed Surface at Phase 03 Completed.
Sub Structure: Backfilling at Phase 03 Completed.
1st Floor: 100% of Stressing, Patching and Grouting for 1st Floor Slab at Pour 01 Area Completed.
1st Floor: 100% of Authority Inspection and Casting of 1st Floor Slab Pour 02 Completed.
1st Floor: 70% De-shuttering of 1st Floor Slab Pour 01 Area Completed.
2nd Floor: 100% Verticals (Columns & Core Walls) 1st to 2nd Floor at Pour 01 Area Completed.
2nd Floor: 100% of Authority Inspection and Casting of 2nd Floor Slab Pour 01 Completed.
2nd Floor: 75% Verticals (Columns & Core Walls) 1st to 2nd Floor at Pour 02 Area Completed.
3rd Floor: 100% of Scaffolding and Shuttering Works for 3rd Floor Slab Pour 01 Completed.
3rd Floor: 50% of Authority Inspection and Casting of 3rd Floor Slab Pour 01 Completed.
3rd Floor: 10% Verticals (Columns & Core Walls) 2nd to 3rd Floor at Pour 02 Area Completed.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 10.50%
Stage:
100% Vertical Columns & Core Walls at Pour Areas 1 to 3 Completed.
100% Reinforcement, PT Works, Inspection and Casting of Pour Area 1 Completed.
De-watering at Water Tank & Pump Room in Phase 1 Area Completed
Reinforcement, Formwork and Casting of Water Tank Top Slab Completed.
Backfilling at Phase 1 and 2 Area Completed.
Levelling, Anti-termite, PCC and Water Proofing below Raft at Phase 4 Completed.
Reinforcement, Formwork and Casting of Raft at Phase 4 Completed.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 7.50%
Stage:
100% of Reinforcement for Raft at Phase 2 Completed.
100% of Form Work/Periphery Block Works for Raft Completed.
100% of Casting of Raft at Phase 2 Completed.
100% of Floor Beams at Phase 2 Completed.
100% of Excavation Works at Phase 3 Completed.
100% of Reinforcement for Footings at Phase 3 Completed.
100% Water Proofing above PCC at Phase 2 Area Completed.
90% Verticals (Columns & Core Walls) at Phase 2 Completed.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 3.75%
Stage:
Mobilization Completed.
Excavation Works for Water Tank & Pump Room Area (Phase-1A) Completed.
Installation of De-Watering System at Water Tank Completed.
100% of Excavation Works at Phase 2 Area Completed.
100% of Levelling and Compaction at Phase 2 Area Completed.
100% of Antitermite and PCC at Phase 2 Area Completed.
100% Water Proofing above PCC at Phase 2 Area Completed.
40% of Reinforcement for Raft at Phase 2 / Pour No.01 Completed.
20% of Form Work/Periphery Block Works for Raft Completed.
60% of Excavation Works at Phase 03 & 04 Area Completed
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 1.01%
Stage:
30% of Excavation Works for Water Tank & Pump Room Area (Phase-1A) Completed.
80% of Excavation Works for Lift Pit Area (Phase-1B) Completed.
30% of Excavation Works at Phase 2 Area Completed.
Launched: 10th October 2022
Planned Handover: 30th April 2024