ZāZEN Gardens – Construction Update

Al Furjan

99%

It is currently under construction and due for completion on 30th April 2024.

This project is registered under RERA project number 2474.

Timeline

Progress:

99%

Stage:

Ground Floor:  Installation of Signages Completed.

Installation of Ironmongeries Completed.

Painting Works Completed.

Entrance Lobby ID Works Completed.

Staircase Epoxy Works Completed

MEP 2nd Fix Works Completed (Electrical, Plumbing, Fire Fighting and HVAC Works).

MEP 3rd Fix Works Completed.

Irrigation Works Completed.

1st Floor :  Painting Works Completed.

Installation of Herbs/Shrubs and Trees Completed.

Landscape & Irrigation Works Completed

MEP 3rd Fix at Flats, Corridor and Service Rooms Completed

Painting Works for Gym & Lounge in Completed.

Open Shower Works Completed.

Installation of Glass Partition in Completed.

Installation of Gym & lounge Aluminium & Glazing Works Completed.

2nd – 4th Floor : Painting Works Completed.

MEP 3rd Fix Works Completed.

Installation of Sanitary Wares Completed.

5th Floor: Painting Works Completed.

Installation of White Goods Completed.

MEP 3rd Fix Works Completed.

Installation of Sanitary Wares Completed.

6th Floor: Painting Works Completed.

Installation of White Goods Completed.

MEP 3rd Fix Works Completed.

Installation of Sanitary Wares Completed.

Roof Floor:  Painting Works Completed

MEP 3rd Fix Works Completed.

Snagging & De-snagging in Progress.

Testing & Commissioning in Progress.

Authority Inspection & Approvals:

  • Dubai Civil Defence: Certificate Obtained
  • Demarcation: Demarcation Certificate Obtained.
  • Nakheel (NCC)  Application for Nakheel (NCC) completed.
  • DEWA (Electrical):  DEWA Power Obtained.
  • DEWA (Water): Construction of Water Meter Chamber Works under progress by DEWA appointed subcontractor.
  • SIRA:  Subcontractor following up with Authority to obtain Final Approval.
  • Building Completion Certificate (BCC): Obtained from Trakhees (EHS & CED).
  • Dubai Land Department Completion: In process.

Launched:

10th October 2022

Planned Handover:

30th April 2024

Progress:

95.36%

Stage:

Ground Floor: Installation of Signages, Ironmongery & Painting Works in Progress. Installation of Glazing, Doors, False Ceiling, Staircase Epoxy, Paving, Irrigation, Fountain Works, all Completed. Entrance Lobby ID Works & MEP 2nd & 3rd Fix Works in Progress.

LV Room: MEP 3rd Fix Works Completed..

1st Floor: 80% Painting Works Completed. Installation of Herbs/Shrubs and Trees in Progress. Landscape & Irrigation Works in Progress. MEP 3rd Fix at Apartments, Corridor and Service Rooms in Progress. Painting Works for Gym & Lounge in Progress.

2 – 4th Floor: Snagging & De-snagging in Progress. 90% of Painting Works Completed. Epoxy for Staircase Completed. MEP 3rd Fix Works in Progress.

5th Floor: 80% of Painting Works Completed. Installation of Glass Partition Completed. Installation of White Goods in Progress. Epoxy for Staircase Completed. MEP 3rd Fix Works in Progress. Installation of Sanitary Ware in Progress.

6th Floor: Dry Area False Ceiling Works Completed. 80% of Painting Works Completed. Installation of Vanity Counter Completed. Installation of Kitchen Completed. Installation of White Goods in Progress. Installation of Glass Partition in Progress. Installation of Sanitary Ware in Progress.

Roof Floor: Installation of LPG Tank & Accessories Completed. Painting Works in Progress MEP 2nd Fix Works Completed. Installation of Louvers/Fence around LPG Tank Completed.

Authority Inspection & Approvals:

  • Dubai Civil Defence: Breaching Inlet Inspection & Approval Completed by DCD
  • Demarcation: Demarcation Certificate Obtained.
  • Nakheel (NCC)  Application for Nakheel (NCC) completed.
  • DEWA (Electrical): 2nd DEWA LV inspection Completed, Payment, Receipt & Installation of Electrical Completed.
  • DEWA (Water): Construction of Water Meter Chamber Works are on hold by DEWA appointed subcontractor. Expected to start next week.

Launched:

10th October 2022

Planned Handover:

30th April 2024

Progress:

89.04%

Stage:

Pump Room: MEP 3rd Fix Works in Progress. Epoxy Works, Installation of Staircase Handrail, Doors & Equipment all Completed.

Ground Floor: 50% of Paving Works (Interlock) Completed. Corridor False Ceiling Works, Installation of Swimming Pool Equipment & Kerbstone Completed. Service Room MEP 2nd & 3rd Fix Works in Progress.

LV Room: MEP 2nd Fix Works Completed. MEP 3rd Fix Works in Progress. Installation of FM 200 Completed.

1st Floor: Balcony Tiling Works, Aluminium & Glazing Works, Landscape, Irrigation & Soil Filling of Planter Box, Installation of Sanitary Wares, Wardrobes, White Goods, Signage, Balcony Tiling & Handrail all Completed Landscape & Irrigation Works in Progress. MEP 3rd Fix at Apts, Corridor and Service Rooms in Progress. Painting Works for Gym & Lounge in Progress.

2nd Floor: 80% of Painting Works Completed. MEP 3rd Fix Works, Installation of White Goods, Sanitary Wares & 1st Coat Paint Completed.

3rd Floor: Installation of Glass Partition, Aluminium & Glazing Works, Installation of Sanitary Wares & MEP 3rd Fix Works Completed. Wall & Ceiling Painting in Progress.

4th Floor: Installation of Kitchen Cabinet, Glass Partition, Wall & Ceiling Painting, Aluminium & Glazing Works, Balcony Handrail, Sanitary Wares all completed. MEP 3rd Fix Works in Progress.

5th Floor: Installation of Doors, Vanity Counter, Kitchen Cabinet, Wet Area Tiling, Corridor False Ceiling Works, Aluminium & Glazing Works & Balcony Handrail Completed. MEP 3rd Fix Works, Wall & Ceiling Painting & Installation of Sanitary Wares in Progress.

6th Floor: Installation of Kitchen Cabinet, Doors, Wardrobe, Ceiling Painting, Wet Area Tiling, Aluminium & Glazing Works, Balcony Handrail Completed. Installation of Sanitary Wares, Wall & Ceiling Painting & MEP 3rd Fix Works in Progress.

Roof Floor: Installation of LPG Tank & Accessories in progress. Painting Works, Planter Box Works & MEP 2nd Fix Works in Progress. Solar PV System Works Completed.

Launched:

10th October 2022

Planned Handover:

30th April 2024

Progress:

80.19%

Stage:

Pump Room: MEP 2nd Fix Works & Equipment Installation Completed. MEP 3rd Fix Works & Epoxy Paint in Progress.
Ground Floor: 25% of Paving Works (Interlock) Completed. Corridor False Ceiling Works Completed. 70% of Installation of Swimming Pool Equipment Completed. Service Room MEP Works, Staircase Epoxy & Wet Area Tiling Works in Progress.
LV Room: MEP 2nd Fix Works in Progress.
1st Floor: Balcony Tiling Works in Progress. Aluminium & Glazing Works 80% Completed. Landscape, Irrigation & Soil Filling of Planter Box in Progress. MEP 3rd Fix for Apts, Corridor and Service Rooms in Progress. Painting Works for Gym & Lounge in Progress. Swimming Pool & Water Body Works in Progress. Wet Area Tiling Works for Gym & Lounge Completed. 1st Coat Paint Completed.
2nd Floor: Installation of Pergola Completed. Installation of Glass Partition Completed. 80% of Painting Works Completed. MEP 3rd Fix Works & LPG installation in Progress. 1st Coat Paint Completed.
3rd Floor: Installation of Kitchen Cabinet & Vanity Counter Completed. Wet Area Tiling & 1st Coat Paint Completed. Installation of Glass Partition in Progress. Wall & Ceiling Painting & Staircase Epoxy in Progress. Aluminium & Glazing Works in Progress. Installation of Balcony Handrail Completed.
Installation of Sanitary Wares in Progress. MEP 3rd Fix Works in Progress.

4th Floor: Installation of Doors & Wet Area Tiling Completed. Installation of Kitchen Cabinet, Glass Partition, Wall & Ceiling Painting, Aluminium & Glazing Works, Balcony Handrail, Sanitary Wares in Progress. MEP 3rd Fix Works in Progress.

5th Floor: Installation of Doors, Vanity Counter, Wet Area Tiling & Corridor False Ceiling Works Completed. Installation of Kitchen Cabinet, Wall & Ceiling Painting, Aluminium & Glazing Works, Balcony Handrail, Sanitary Wares in Progress. MEP 3rd Fix Works in Progress.

6th Floor: Dry Area False Ceiling Works & Corridor False Ceiling Works Completed.

Installation of Kitchen Cabinet, Doors, Vanity Counter, & Ceiling Painting, Aluminium & Glazing Works, Balcony Handrail, Sanitary Wares in Progress. MEP 3rd Fix Works in Progress.

Roof Floor: Installation of LPG Tank & Accessories in progress. Painting Works, Planter Box Works & MEP 2nd Fix Works in Progress.

Launched: 10th October 2022
Planned Handover: 30th April 2024

Progress:

72.09%

Stage:

Pump Room: Installation of Equipment in Progress & MEP 3rd Fix in Progress.
Ground Floor: 30% of Corridor Suspension Works Completed. 30% of Installation of Swimming Pool Equipment Completed. MEP 2nd Fix Works in Progress. Service Room MEP Works in Progress.
LV Room: MEP 2nd Fix Works in Progress.
1st Floor: Wall & Ceiling Painting, Balcony Upstand, False Ceiling Works, Installation of Kitchen Cabinets & Wardrobes all Completed.
1st Floor: MEP 3rd Fix in Apartments & MEP 2nd Fix Works for Gym & Lounge in Progress. Aluminium & Glazing Works, Swimming Pool & Water Body Works in Progress.
2nd Floor: Wall & Ceiling Painting, Balcony & Corridor Tiling, Vanity Counter Works, Kitchen Cabinet Works, Sanitary Ware installation & MEP 2nd all Completed. MEP 3rd Fix Works & LPG installation in Progress.
3rd & 4th Floor: Wall & Ceiling Painting, Balcony & Corridor Tiling, Aluminium & Glazing Works, Sanitary Ware installation all in Progress. MEP 2nd Fix Completed. MEP 3rd Fix Works in Progress.
5th & 6th Floor: Wall & Ceiling Painting, Aluminium & Glazing Works, Balcony and Corridor Tiling Works, False Ceiling Works, MEP 2nd & 3rd Fix all in Progress.
Roof Floor: Erection of Steel Structure Completed. Solar Works Completed. MEP 2nd Fix Works in Progress.
Façade: 95% of External Painting for Façade (1st Floor to Roof Floor) Completed. Ground Floor Aluminium Screens / Louvers in Progress.

Launched:

10th October 2022

Planned Handover:

30th April 2024

Progress:

65.52%

Stage:

Pump Room: Installation of Equipment in Progress & MEP 3rd Fix in Progress.

Ground Floor: 100% of Block Work, Ceiling & Corridor Plaster Completed. MEP 2nd Fix Works in Progress. Installation of Generator Completed.

LV Room: MEP 2nd Fix Works in Progress.

1st Floor: Wall & Ceiling Painting, Balcony Upstand, False Ceiling Works all in Progress.

1st Floor: Wall & Ceiling Painting, Tiling Works, Kitchen Cabinet Works, MEP 2nd Fix in Progress. 100% of Block Works at Gym & Lounge Completed. Swimming Pool Works in Progress.

2nd Floor: Wall & Ceiling Painting, Balcony & Corridor Tiling, Vanity Counter Works, Kitchen Cabinet Works, Sanitary Ware installation,  MEP 2nd & 3rd Fix all in Progress.

3rd & 4th Floor: Wall & Ceiling Painting, Balcony & Corridor Tiling, Aluminium & Glazing Works, Sanitary Ware installation, MEP 2nd & 3rd Fix all in Progress.

5th & 6th Floor: Wall & Ceiling Painting, Aluminium & Glazing Works, Balcony and Corridor Tiling Works, False Ceiling Works, MEP 2nd & 3rd Fix all in Progress.

Roof Floor: Roof Water Proofing Completed. Erection of Steel Structure Works for Solar in Progress. MEP 2nd Fix Works in Progress.

Façade: External Painting for Façade (1st Floor to Roof Floor) in Progress. Ground Floor Aluminium Screens / Louvers in Progress.

Launched:

10th October 2022

Planned Handover:

30th April 2024

Progress: 58.32%
Stage:
Pump Room: Staircase Surface Epoxy Completed. Primer, Stucco & MEP 3rd Fix in Progress.
Ground Floor: 90% of Ceiling & Corridor Plaster Completed. Service Room MEP Works & Installation of Generator in Progress.
LV Room: MEP 2nd Fix Works in Progress.
1st Floor: Wall & Ceiling Painting, Balcony Upstand, False Ceiling Works all in Progress.
1st Floor: 100% Erection of Steel Structure for Gym Completed. 60% of Block Works at Gym & Lounge in Progress. Aluminium & Glazing Works in Progress.
2nd Floor: Wall & Ceiling Painting, Balcony Upstand, False Ceiling Works, Kitchen Cabinet Works all in Progress.
3rd & 4th Floor: MEP 2nd Fix for Apartments Completed.  False Ceiling Works in Progress. MEP 3rd Fix Completed.
5th Floor: 100% of Internal Plastering & Corridor Plastering Completed. MEP 2nd Fix  & False Ceiling Under Progress.
6th Floor: 100% of Plastering Works Completed. Tiling Works in Dry Area and Wet Area in Progress. 100% of Corridor Plaster Completed.
Façade: External Plaster Ground Floor to 1st Floor & Façade Completed. Ground Floor Aluminium Screens / Louvers in Progress.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 52.23%
Stage:
Pump Room: Installation of Equipment in Progress.
Ground Floor: 99% of Block Work Completed. 70% of Tiling Work Completed. MEP 2nd Fix Under Progress.
Substation: DEWA Authority approval obtained.
1st Floor: MEP 2nd Fix for Apartments Under Progress.
1st Floor: Installation of Sanitary Ware in Progress.
2nd Floor: MEP 2nd Fix for Apartments Under Progress. Balcony Tiling in Progress.
3rd & 4th Floor: MEP 2nd Fix for Apartments Under Progress. Plastering Works Completed.
5th Floor: 90% of Plastering, Wall & Ceiling Painting & Balcony Plaster Completed.
6th Floor: Block Work Completed. 30% of Ceiling Preparation Completed. MEP 1st Fix Completed.
Façade: External Plaster & Painting for Façade in Progress.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 47.50%
Stage:
Pump Room: Foundation Completed. Installation of Equipment in Progress.
Ground Floor: 90% of Block Work Completed. 80% of Ceiling Painting/Plaster Completed.
Substation: Work Completed. DEWA Authority Inspection for Substation applied.
1st Floor: Plastering Completed. Wall & Ceiling Painting in Progress.
1st Floor: Tiling Works, False Ceiling Work, Upstand for Balconies & Partition works in Progress.
3rd & 4th Floor: Plastering, Wall & Ceiling Painting, Tiling in Wet Area, Upstand & MEP 2nd Fix works in Progress.
5th Floor: Plastering, Wall & Ceiling Painting & MEP 2nd Fix works in Progress.
6th Floor: MEP 1st Fix & 2nd Fix work in Progress.
Façade: External Plaster Ground Floor to 1st Floor Completed. External Plaster for Façade in Progress.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 41.49%
Stage:
Ground Floor: Plant Room Plastering Completed.
Ground Floor: MEP 2nd Fix in Progress (Electrical, Plumbing, Fire Fighting and HVAC).
Substation: Plaster Preparation Completed. Painting in Progress.
1st Floor: Block Work & MEP 1st Fix Works Completed.
1st Floor: Plastering & MEP 2nd Fix Works in Progress.
2nd Floor: Plastering & MEP 1st Fix Works in Progress.
3rd & 4th Floor: Block Work Completed. MEP 1st Fix Works in Progress.
5th Floor: 75% of Block Work Completed.
6th Floor: 60% of Block Work Completed.
Roof Floor: De-Shuttering of Roof at Pour 02 Completed.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 38.25%
Stage:
Ground Floor: Block Work and Ceiling Painting/Plaster in Progress.
Ground Floor: MEP 1st Fix Completed, 2nd Fix in Progress.
Substation: Block Work and MEP 1st Fix Works Completed.
1st Floor: 95% of Block Work Completed.
1st Floor: MEP 1st & 2nd Fix Works in Progress.
2nd Floor: 97% of Block Work Completed. MEP 1st Fix Works Under Progress.
3rd & 4th Floor: 75% of Block Work Completed.
5th Floor: De-Shuttering of 5th Floor, Pour 01 & 02 Completed. 20% of Block Work Completed.
6th Floor: Casting of 6th Floor Slab Pour 01 & 02 Completed. 15% of Block Work Completed.
Roof Floor: Casting of Slab 02 Completed. 15% of Block Work Completed. De-Shuttering in Progress.
Swimming Pool: Structural Works and Plaster for Swimming Pool Completed.
Facade: External Plaster from Ground to 1st Floor Completed.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 31.35%
Stage:
Ground Floor: Plaster Preparation and Plaster for Lobby and Staircase Completed.
Ground Floor: Block Work, Ceiling Painting and Plaster Works in Progress.
Substation: Casting of Trench Completed and Block Work in Progress.
1st Floor: De-Shuttering of 1st Floor Slab at Pour 03 Completed.
1st to 3rd Floor: Block Work in Progress.
4th Floor: Casting of 4th Floor Slab Pour 02 Completed. Block Work in Progress.
4th Floor: De-Shuttering of 4th Floor Slab Pour 01 & 02 Completed.
5th Floor: Casting and Vertical Works at 5th Floor Slab Pour 02 Completed.
6th Floor: Casting of Verticals and Floor Slab at 6th Floor Pour 01 & 02 Completed.
Roof Floor: Casting of Verticals and Floor Slab at Roof Pour 01 Completed and Pour 02 in Progress.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 23.22%
Stage:
Underground: Tank Cleaning and Preparation of Tanks are in Progress.
Underground: Pump Room Plaster Preparation Completed and MEP 1st Fix Works in Progress.
1st Floor: Casting of 1st Floor Slab Pour 03 Completed.
1st Floor: De-Shuttering of 1st Floor Slab at Pour 01 & 02 Completed.
1st Floor: Stressing & Patching for 1st Floor at Pour 01, 02 & 03 Completed.
2nd Floor: Casting and De-Shuttering of 2nd Floor Slab Pour 02 Completed.
3rd Floor: Casting and De-Shuttering of 3rd Floor Slab Pour 01 & 02 Completed.
4th Floor: Casting of 4th Floor Slab Pour 01 Completed. Pour 02 is Partially Completed.
4th Floor: Stressing & Patching for 4th Floor at Pour 01 Completed and Pour 02 in Progress.
5th Floor: Casting of 5th Floor Slab Pour 01 Completed. Vertical Works at 5th Floor Pour 02 in Progress.
6th Floor: Casting of Verticals at 6th Floor Slab Pour 01 in Progress. Scaffolding & Shuttering Works at 6th Floor at Pour 01 in Progress.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 16.22%
Stage:
Sub Structure: Water Proofing for Exposed Surface at Phase 03 Completed.
Sub Structure: Backfilling at Phase 03 Completed.
1st Floor: 100% of Stressing, Patching and Grouting for 1st Floor Slab at Pour 01 Area Completed.
1st Floor: 100% of Authority Inspection and Casting of 1st Floor Slab Pour 02 Completed.
1st Floor: 70% De-shuttering of 1st Floor Slab Pour 01 Area Completed.
2nd Floor: 100% Verticals (Columns & Core Walls) 1st to 2nd Floor at Pour 01 Area Completed.
2nd Floor: 100% of Authority Inspection and Casting of 2nd Floor Slab Pour 01 Completed.
2nd Floor: 75% Verticals (Columns & Core Walls) 1st to 2nd Floor at Pour 02 Area Completed.
3rd Floor: 100% of Scaffolding and Shuttering Works for 3rd Floor Slab Pour 01 Completed.
3rd Floor: 50% of Authority Inspection and Casting of 3rd Floor Slab Pour 01 Completed.
3rd Floor: 10% Verticals (Columns & Core Walls) 2nd to 3rd Floor at Pour 02 Area Completed.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 10.50%
Stage:
100% Vertical Columns & Core Walls at Pour Areas 1 to 3 Completed.
100% Reinforcement, PT Works, Inspection and Casting of Pour Area 1 Completed.
De-watering at Water Tank & Pump Room in Phase 1 Area Completed
Reinforcement, Formwork and Casting of Water Tank Top Slab Completed.
Backfilling at Phase 1 and 2 Area Completed.
Levelling, Anti-termite, PCC and Water Proofing below Raft at Phase 4 Completed.
Reinforcement, Formwork and Casting of Raft at Phase 4 Completed.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 7.50%
Stage:
100% of Reinforcement for Raft at Phase 2 Completed.
100% of Form Work/Periphery Block Works for Raft Completed.
100% of Casting of Raft at Phase 2 Completed.
100% of Floor Beams at Phase 2 Completed.
100% of Excavation Works at Phase 3 Completed.
100% of Reinforcement for Footings at Phase 3 Completed.
100% Water Proofing above PCC at Phase 2 Area Completed.
90% Verticals (Columns & Core Walls) at Phase 2 Completed.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 3.75%
Stage:
Mobilization Completed.
Excavation Works for Water Tank & Pump Room Area (Phase-1A) Completed.
Installation of De-Watering System at Water Tank Completed.
100% of Excavation Works at Phase 2 Area Completed.
100% of Levelling and Compaction at Phase 2 Area Completed.
100% of Antitermite and PCC at Phase 2 Area Completed.
100% Water Proofing above PCC at Phase 2 Area Completed.
40% of Reinforcement for Raft at Phase 2 / Pour No.01 Completed.
20% of Form Work/Periphery Block Works for Raft Completed.
60% of Excavation Works at Phase 03 & 04 Area Completed
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 1.01%
Stage:
30% of Excavation Works for Water Tank & Pump Room Area (Phase-1A) Completed.
80% of Excavation Works for Lift Pit Area (Phase-1B) Completed.
30% of Excavation Works at Phase 2 Area Completed.
Launched: 10th October 2022
Planned Handover: 30th April 2024