ZāZEN Gardens – Construction Update

Al Furjan

7.50%

It is currently under construction and due for completion on 30th April 2024.

This project is registered under RERA project number 2474.

Timeline

Progress: 7.50%
Stage:
100% of Reinforcement for Raft at Phase 2 Completed.
100% of Form Work/Periphery Block Works for Raft Completed.
100% of Casting of Raft at Phase 2 Completed.
100% of Floor Beams at Phase 2 Completed.
100% of Excavation Works at Phase 3 Completed.
100% of Reinforcement for Footings at Phase 3 Completed.
100% Water Proofing above PCC at Phase 2 Area Completed.
90% Verticals (Columns & Core Walls) at Phase 2 Completed.
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 3.75%
Stage:
Mobilization Completed.
Excavation Works for Water Tank & Pump Room Area (Phase-1A) Completed.
Installation of De-Watering System at Water Tank Completed.
100% of Excavation Works at Phase 2 Area Completed.
100% of Levelling and Compaction at Phase 2 Area Completed.
100% of Antitermite and PCC at Phase 2 Area Completed.
100% Water Proofing above PCC at Phase 2 Area Completed.
40% of Reinforcement for Raft at Phase 2 / Pour No.01 Completed.
20% of Form Work/Periphery Block Works for Raft Completed.
60% of Excavation Works at Phase 03 & 04 Area Completed
Launched: 10th October 2022
Planned Handover: 30th April 2024
Progress: 1.01%
Stage:
30% of Excavation Works for Water Tank & Pump Room Area (Phase-1A) Completed.
80% of Excavation Works for Lift Pit Area (Phase-1B) Completed.
30% of Excavation Works at Phase 2 Area Completed.
Launched: 10th October 2022
Planned Handover: 30th April 2024