The Hub Residences by ZāZEN – Construction Update

Al Furjan

5.15%

It is currently under construction and is planned for completion in January 2027 .

This project is registered under RERA project number 3419.

Timeline

Progress:  5.15%
Stage: Excavation Works:
· Main raft area – 85% completed.· Staircase & UG water tank – 100% completed.· UG pump room & sump pit – 80% completed.

Dewatering Works:
· Dewatering – Under progress.

Road base & Compaction Works:
· Main raft foundation area – 70% completed.· Isolated footing – 85% completed.· UG staircase– 100% completed.· UG Water tank & Pump room – 80% completed.

Solid Block Works:
· Solid Block works for main raft area – 75% completed.

PCC Works:
· PCC below Raft foundation – 50% completed.· PCC Below Isolated footing – 85% completed.

Waterproofing & Reinforcement Works:
· Waterproofing membrane below Main Raft foundation – 50% completed.· Waterproofing membrane below Isolated footing – 75% completed.
Steel reinforcement work for the Isolated footing & substation – 50% completed.

Construction Start:     July 2025
Planned Completion:     January 2027
Progress:  2.86%
Stage: Mobilization Works

  • Site Office, 100% completed.

Excavation Works

  • Excavation for Lift pit, 100% completed.
  • Excavation for Water tank & pump room, 50% completed.
  • Compaction of Main Excavation Area, 50% completed.

Dewatering Works

  • Mobilization for Dewatering works, 100% completed.
  • Dewatering, under progress.

Roadbase Works

  • Compaction, Leveling and Laying of roadbase, 50% completed.

Solid Block Works

  • Substation and lift area, 50% completed.

PCC Works

  • PCC work below the Raft foundation, 50% completed.
Construction Start:     July 2025
Planned Completion:     January 2027
Progress:       1.00%
Stage:       Mobilization Works:

  • Site Office, 75% completed.
  • Sign Board Erection, 100% completed.
  • Store & Labor rest room, 100% completed.

Excavation Works:

  • Excavation for main area, 100% completed.
  • Excavation for water tank & pump room, 50% completed.

Dewatering Works:

  • Mobilization for De-watering works, 50% completed.
Construction Start:     July 2025
Planned Completion:     January 2027