The Hub Residences by ZāZEN – Construction Update

Al Furjan

2.86%

It is currently under construction and is planned for completion in January 2027 .

This project is registered under RERA project number 3419.

Timeline

 
Progress:  2.86%
Stage:

Mobilization Works

  • Site Office, 100% completed.

Excavation Works

  • Excavation for Lift pit, 100% completed.
  • Excavation for Water tank & pump room, 50% completed.
  • Compaction of Main Excavation Area, 50% completed.

Dewatering Works

  • Mobilization for Dewatering works, 100% completed.
  • Dewatering, under progress.

Roadbase Works

  • Compaction, Leveling and Laying of roadbase, 50% completed.

Solid Block Works

  • Substation and lift area, 50% completed.

PCC Works

  • PCC work below the Raft foundation, 50% completed.
Construction Start:     July 2025
Planned Completion:     January 2027
Progress:       1.00%
Stage:       Mobilization Works:

  • Site Office, 75% completed.
  • Sign Board Erection, 100% completed.
  • Store & Labor rest room, 100% completed.

Excavation Works:

  • Excavation for main area, 100% completed.
  • Excavation for water tank & pump room, 50% completed.

Dewatering Works:

  • Mobilization for De-watering works, 50% completed.
Construction Start:     July 2025
Planned Completion:     January 2027