Zazen Gardens Construction Updates
100%
Complete
ZāZEN GARDENS
CONSTRUCTION UPDATES
Start Date
OCT 2022
Completion DateApr 2024
This project was delivered on time and handed over on April 30th 2024
TIMELINE
ZāZEN GARDENS – CONSTRUCTION UPDATE
Progress
100%
Stage
Delivered on 30th April
Launched
10th October 2022
Planned Handover
30th April 2024









Progress
99%
Stage
Ground Floor:
- Installation of Signages Completed
- Installation of Ironmongeries Completed
- Painting Works Completed
- Entrance Lobby ID Works Completed
- Staircase Epoxy Works Completed
- MEP 2nd Fix Works Completed (Electrical, Plumbing, Fire Fighting and HVAC Works)
- MEP 3rd Fix Works Completed
- Irrigation Works Completed
1st Floor:
- Painting Works Completed
- Installation of Herbs/Shrubs and Trees Completed
- Landscape & Irrigation Works Completed
- MEP 3rd Fix at Flats, Corridor and Service Rooms Completed
- Painting Works for Gym & Lounge Completed
- Open Shower Works Completed
- Installation of Glass Partition Completed
- Installation of Gym & Lounge Aluminium & Glazing Works Completed
2nd – 4th Floor:
- Painting Works Completed
- MEP 3rd Fix Works Completed
- Installation of Sanitary Wares Completed
5th Floor:
- Painting Works Completed
- Installation of White Goods Completed
- MEP 3rd Fix Works Completed
- Installation of Sanitary Wares Completed
6th Floor:
- Painting Works Completed
- Installation of White Goods Completed
- MEP 3rd Fix Works Completed
- Installation of Sanitary Wares Completed
Roof Floor:
- Painting Works Completed
- MEP 3rd Fix Works Completed
- Snagging & De-snagging in Progress
- Testing & Commissioning in Progress
Authority Inspection & Approvals:
- Dubai Civil Defence: Certificate Obtained
- Demarcation: Demarcation Certificate Obtained
- Nakheel (NCC): Application completed
- DEWA (Electrical): DEWA Power Obtained
- DEWA (Water): Construction of Water Meter Chamber Works under progress by DEWA appointed subcontractor
- SIRA: Subcontractor following up with Authority to obtain Final Approval
- Building Completion Certificate (BCC): Obtained from Trakhees (EHS & CED)
- Dubai Land Department Completion: In process
Launched
10th October 2022
Planned Handover
30th April 2024









Progress
95.36%
Stage
Ground Floor:
- Installation of Signages, Ironmongery & Painting Works in Progress
- Installation of Glazing, Doors, False Ceiling, Staircase Epoxy, Paving, Irrigation, Fountain Works Completed
- Entrance Lobby ID Works in Progress
- MEP 2nd & 3rd Fix Works in Progress
LV Room:
- MEP 3rd Fix Works Completed
1st Floor:
- 80% Painting Works Completed
- Installation of Herbs/Shrubs and Trees in Progress
- Landscape & Irrigation Works in Progress
- MEP 3rd Fix at Apartments, Corridor and Service Rooms in Progress
- Painting Works for Gym & Lounge in Progress
2nd – 4th Floor:
- Snagging & De-snagging in Progress
- 90% of Painting Works Completed
- Epoxy for Staircase Completed
- MEP 3rd Fix Works in Progress
5th Floor:
- 80% of Painting Works Completed
- Installation of Glass Partition Completed
- Installation of White Goods in Progress
- Epoxy for Staircase Completed
- MEP 3rd Fix Works in Progress
- Installation of Sanitary Ware in Progress
6th Floor:
- Dry Area False Ceiling Works Completed
- 80% of Painting Works Completed
- Installation of Vanity Counter Completed
- Installation of Kitchen Completed
- Installation of White Goods in Progress
- Installation of Glass Partition in Progress
- Installation of Sanitary Ware in Progress
Roof Floor:
- Installation of LPG Tank & Accessories Completed
- Painting Works in Progress
- MEP 2nd Fix Works Completed
- Installation of Louvers/Fence around LPG Tank Completed
Authority Inspection & Approvals:
- Dubai Civil Defence: Breaching Inlet Inspection & Approval Completed by DCD
- Demarcation: Demarcation Certificate Obtained
- Nakheel (NCC): Application Completed
- DEWA (Electrical): 2nd DEWA LV Inspection Completed, Payment, Receipt & Installation Completed
- DEWA (Water): Water Meter Chamber Works on hold by DEWA subcontractor (Expected to start next week)
Launched
10th October 2022
Planned Handover
30th April 2024






Progress
89.04%
Stage
Pump Room:
- MEP 3rd Fix Works in Progress
- Epoxy Works Completed
- Installation of Staircase Handrail Completed
- Doors & Equipment Installation Completed
Ground Floor:
- 50% of Paving Works (Interlock) Completed
- Corridor False Ceiling Works Completed
- Installation of Swimming Pool Equipment Completed
- Kerbstone Works Completed
- Service Room MEP 2nd & 3rd Fix Works in Progress
LV Room:
- MEP 2nd Fix Works Completed
- MEP 3rd Fix Works in Progress
- Installation of FM 200 Completed
1st Floor:
- Balcony Tiling Works Completed
- Aluminium & Glazing Works Completed
- Landscape, Irrigation & Soil Filling of Planter Box Completed
- Installation of Sanitary Wares Completed
- Installation of Wardrobes Completed
- Installation of White Goods Completed
- Signage, Balcony Tiling & Handrail Completed
- Landscape & Irrigation Works in Progress
- MEP 3rd Fix at Apts, Corridor & Service Rooms in Progress
- Painting Works for Gym & Lounge in Progress
2nd Floor:
- 80% of Painting Works Completed
- MEP 3rd Fix Works Completed
- Installation of White Goods Completed
- Installation of Sanitary Wares Completed
- 1st Coat Paint Completed
3rd Floor:
- Installation of Glass Partition Completed
- Aluminium & Glazing Works Completed
- Installation of Sanitary Wares Completed
- MEP 3rd Fix Works Completed
- Wall & Ceiling Painting in Progress
4th Floor:
- Installation of Kitchen Cabinet Completed
- Installation of Glass Partition Completed
- Wall & Ceiling Painting Completed
- Aluminium & Glazing Works Completed
- Balcony Handrail Completed
- Installation of Sanitary Wares Completed
- MEP 3rd Fix Works in Progress
5th Floor:
- Installation of Doors Completed
- Installation of Vanity Counter Completed
- Installation of Kitchen Cabinet Completed
- Wet Area Tiling Completed
- Corridor False Ceiling Works Completed
- Aluminium & Glazing Works Completed
- Balcony Handrail Completed
- MEP 3rd Fix Works in Progress
- Wall & Ceiling Painting in Progress
- Installation of Sanitary Wares in Progress
6th Floor:
- Installation of Kitchen Cabinet Completed
- Installation of Doors Completed
- Installation of Wardrobe Completed
- Ceiling Painting Completed
- Wet Area Tiling Completed
- Aluminium & Glazing Works Completed
- Balcony Handrail Completed
- Installation of Sanitary Wares in Progress
- Wall & Ceiling Painting in Progress
- MEP 3rd Fix Works in Progress
Roof Floor:
- Installation of LPG Tank & Accessories in Progress
- Painting Works in Progress
- Planter Box Works in Progress
- MEP 2nd Fix Works in Progress
- Solar PV System Works Completed
Launched
10th October 2022
Planned Handover
30th April 2024






Progress
80.19%
Stage
Pump Room:
- MEP 2nd Fix Works & Equipment Installation Completed
- MEP 3rd Fix Works in Progress
- Epoxy Paint in Progress
Ground Floor:
- 25% of Paving Works (Interlock) Completed
- Corridor False Ceiling Works Completed
- 70% of Installation of Swimming Pool Equipment Completed
- Service Room MEP Works in Progress
- Staircase Epoxy in Progress
- Wet Area Tiling Works in Progress
LV Room:
- MEP 2nd Fix Works in Progress
1st Floor:
- Balcony Tiling Works in Progress
- Aluminium & Glazing Works 80% Completed
- Landscape, Irrigation & Soil Filling of Planter Box in Progress
- MEP 3rd Fix for Apts, Corridor & Service Rooms in Progress
- Painting Works for Gym & Lounge in Progress
- Swimming Pool & Water Body Works in Progress
- Wet Area Tiling Works for Gym & Lounge Completed
- 1st Coat Paint Completed
2nd Floor:
- Installation of Pergola Completed
- Installation of Glass Partition Completed
- 80% of Painting Works Completed
- MEP 3rd Fix Works in Progress
- LPG Installation in Progress
- 1st Coat Paint Completed
3rd Floor:
- Installation of Kitchen Cabinet & Vanity Counter Completed
- Wet Area Tiling Completed
- 1st Coat Paint Completed
- Installation of Glass Partition in Progress
- Wall & Ceiling Painting in Progress
- Staircase Epoxy in Progress
- Aluminium & Glazing Works in Progress
- Installation of Balcony Handrail Completed
- Installation of Sanitary Wares in Progress
- MEP 3rd Fix Works in Progress
4th Floor:
- Installation of Doors Completed
- Wet Area Tiling Completed
- Installation of Kitchen Cabinet in Progress
- Installation of Glass Partition in Progress
- Wall & Ceiling Painting in Progress
- Aluminium & Glazing Works in Progress
- Balcony Handrail in Progress
- Installation of Sanitary Wares in Progress
- MEP 3rd Fix Works in Progress
5th Floor:
- Installation of Doors Completed
- Installation of Vanity Counter Completed
- Wet Area Tiling Completed
- Corridor False Ceiling Works Completed
- Installation of Kitchen Cabinet in Progress
- Wall & Ceiling Painting in Progress
- Aluminium & Glazing Works in Progress
- Balcony Handrail in Progress
- Installation of Sanitary Wares in Progress
- MEP 3rd Fix Works in Progress
6th Floor:
- Dry Area False Ceiling Works Completed
- Corridor False Ceiling Works Completed
- Installation of Kitchen Cabinet in Progress
- Installation of Doors in Progress
- Installation of Vanity Counter in Progress
- Ceiling Painting in Progress
- Aluminium & Glazing Works in Progress
- Balcony Handrail in Progress
- Installation of Sanitary Wares in Progress
- MEP 3rd Fix Works in Progress
Roof Floor:
- Installation of LPG Tank & Accessories in Progress
- Painting Works in Progress
- Planter Box Works in Progress
- MEP 2nd Fix Works in Progress
Launched
10th October 2022
Planned Handover
30th April 2024






Progress
72.09%
Stage
Pump Room:
- Installation of Equipment in Progress
- MEP 3rd Fix in Progress
Ground Floor:
- 30% of Corridor Suspension Works Completed
- 30% of Installation of Swimming Pool Equipment Completed
- MEP 2nd Fix Works in Progress
- Service Room MEP Works in Progress
LV Room:
- MEP 2nd Fix Works in Progress
1st Floor:
- Wall & Ceiling Painting Completed
- Balcony Upstand Completed
- False Ceiling Works Completed
- Installation of Kitchen Cabinets Completed
- Installation of Wardrobes Completed
- MEP 3rd Fix in Apartments in Progress
- MEP 2nd Fix Works for Gym & Lounge in Progress
- Aluminium & Glazing Works in Progress
- Swimming Pool & Water Body Works in Progress
2nd Floor:
- Wall & Ceiling Painting Completed
- Balcony & Corridor Tiling Completed
- Vanity Counter Works Completed
- Kitchen Cabinet Works Completed
- Sanitary Ware Installation Completed
- MEP 2nd Fix Completed
- MEP 3rd Fix Works in Progress
- LPG Installation in Progress
3rd & 4th Floor:
- Wall & Ceiling Painting in Progress
- Balcony & Corridor Tiling in Progress
- Aluminium & Glazing Works in Progress
- Sanitary Ware Installation in Progress
- MEP 2nd Fix Completed
- MEP 3rd Fix Works in Progress
5th & 6th Floor:
- Wall & Ceiling Painting in Progress
- Aluminium & Glazing Works in Progress
- Balcony & Corridor Tiling Works in Progress
- False Ceiling Works in Progress
- MEP 2nd & 3rd Fix Works in Progress
Roof Floor:
- Erection of Steel Structure Completed
- Solar Works Completed
- MEP 2nd Fix Works in Progress
Façade:
- 95% of External Painting for Façade (1st Floor to Roof Floor) Completed
- Ground Floor Aluminium Screens / Louvers in Progress
Launched
10th October 2022
Planned Handover
30th April 2024







Progress
65.52%
Stage
Pump Room:
- Installation of Equipment in Progress
- MEP 3rd Fix in Progress
Ground Floor:
- 100% of Block Work Completed
- 100% of Ceiling Completed
- 100% of Corridor Plaster Completed
- MEP 2nd Fix Works in Progress
- Installation of Generator Completed
LV Room:
- MEP 2nd Fix Works in Progress
1st Floor:
- Wall & Ceiling Painting in Progress
- Balcony Upstand in Progress
- False Ceiling Works in Progress
- Tiling Works in Progress
- Kitchen Cabinet Works in Progress
- MEP 2nd Fix in Progress
- 100% Block Works at Gym & Lounge Completed
- Swimming Pool Works in Progress
2nd Floor:
- Wall & Ceiling Painting in Progress
- Balcony & Corridor Tiling in Progress
- Vanity Counter Works in Progress
- Kitchen Cabinet Works in Progress
- Sanitary Ware Installation in Progress
- MEP 2nd Fix in Progress
- MEP 3rd Fix in Progress
3rd & 4th Floor:
- Wall & Ceiling Painting in Progress
- Balcony & Corridor Tiling in Progress
- Aluminium & Glazing Works in Progress
- Sanitary Ware Installation in Progress
- MEP 2nd Fix in Progress
- MEP 3rd Fix in Progress
5th & 6th Floor:
- Wall & Ceiling Painting in Progress
- Aluminium & Glazing Works in Progress
- Balcony & Corridor Tiling Works in Progress
- False Ceiling Works in Progress
- MEP 2nd & 3rd Fix in Progress
Roof Floor:
- Roof Waterproofing Completed
- Erection of Steel Structure Works for Solar in Progress
- MEP 2nd Fix Works in Progress
Façade:
- External Painting for Façade (1st Floor to Roof Floor) in Progress
- Ground Floor Aluminium Screens / Louvers in Progress
Launched
10th October 2022
Planned Handover
30th April 2024







Progress
58.32%
Stage
Pump Room:
- Staircase Surface Epoxy Completed
- Primer in Progress
- Stucco in Progress
- MEP 3rd Fix in Progress
Ground Floor:
- 90% of Ceiling & Corridor Plaster Completed
- Service Room MEP Works in Progress
- Installation of Generator in Progress
LV Room:
- MEP 2nd Fix Works in Progress
1st Floor:
- Wall & Ceiling Painting in Progress
- Balcony Upstand in Progress
- False Ceiling Works in Progress
- 100% Erection of Steel Structure for Gym Completed
- 60% of Block Works at Gym & Lounge in Progress
- Aluminium & Glazing Works in Progress
2nd Floor:
- Wall & Ceiling Painting in Progress
- Balcony Upstand in Progress
- False Ceiling Works in Progress
- Kitchen Cabinet Works in Progress
3rd & 4th Floor:
- MEP 2nd Fix for Apartments Completed
- False Ceiling Works in Progress
- MEP 3rd Fix Completed
5th Floor:
- 100% of Internal Plastering Completed
- 100% of Corridor Plastering Completed
- MEP 2nd Fix in Progress
- False Ceiling Under Progress
6th Floor:
- 100% of Plastering Works Completed
- Tiling Works in Dry Area in Progress
- Tiling Works in Wet Area in Progress
- 100% of Corridor Plaster Completed
Façade:
- External Plaster Ground Floor to 1st Floor Completed
- Façade Plaster Completed
- Ground Floor Aluminium Screens / Louvers in Progress
Launched
10th October 2022
Planned Handover
30th April 2024






Progress
52.23%
Stage
Pump Room:
- Installation of Equipment in Progress
Ground Floor:
- 99% of Block Work Completed
- 70% of Tiling Work Completed
- MEP 2nd Fix Under Progress
Substation:
- DEWA Authority approval obtained
1st Floor:
- MEP 2nd Fix for Apartments Under Progress
- Installation of Sanitary Ware in Progress
2nd Floor:
- MEP 2nd Fix for Apartments Under Progress
- Balcony Tiling in Progress
3rd & 4th Floor:
- MEP 2nd Fix for Apartments Under Progress
- Plastering Works Completed
5th Floor:
- 90% of Plastering Completed
- Wall & Ceiling Painting Completed
- Balcony Plaster Completed
6th Floor:
- Block Work Completed
- 30% of Ceiling Preparation Completed
- MEP 1st Fix Completed
Façade:
- External Plaster & Painting for Façade in Progress
Launched
10th October 2022
Planned Handover
30th April 2024






Progress
47.50%
Stage
Pump Room:
- Foundation Completed
- Installation of Equipment in Progress
Ground Floor:
- 90% of Block Work Completed
- 80% of Ceiling Painting/Plaster Completed
Substation:
- Work Completed
- DEWA Authority Inspection for Substation applied
1st Floor:
- Plastering Completed
- Wall & Ceiling Painting in Progress
- Tiling Works in Progress
- False Ceiling Work in Progress
- Upstand for Balconies & Partition Works in Progress
3rd & 4th Floor:
- Plastering in Progress
- Wall & Ceiling Painting in Progress
- Tiling in Wet Area in Progress
- Upstand Works in Progress
- MEP 2nd Fix Works in Progress
5th Floor:
- Plastering in Progress
- Wall & Ceiling Painting in Progress
- MEP 2nd Fix Works in Progress
6th Floor:
- MEP 1st Fix in Progress
- MEP 2nd Fix in Progress
Façade:
- External Plaster Ground Floor to 1st Floor Completed
- External Plaster for Façade in Progress
Launched
10th October 2022
Planned Handover
30th April 2024






Progress
41.49%
Stage
Ground Floor:
- Plant Room Plastering Completed
- MEP 2nd Fix in Progress (Electrical, Plumbing, Fire Fighting and HVAC)
Substation:
- Plaster Preparation Completed
- Painting in Progress
1st Floor:
- Block Work & MEP 1st Fix Works Completed
- Plastering & MEP 2nd Fix Works in Progress
2nd Floor:
- Plastering in Progress
- MEP 1st Fix Works in Progress
3rd & 4th Floor:
- Block Work Completed
- MEP 1st Fix Works in Progress
5th Floor:
- 75% of Block Work Completed
6th Floor:
- 60% of Block Work Completed
Roof Floor:
- De-Shuttering of Roof at Pour 02 Completed
Launched
10th October 2022
Planned Handover
30th April 2024





Progress
38.25%
Stage
Ground Floor:
- Block Work and Ceiling Painting/Plaster in Progress
- MEP 1st Fix Completed, 2nd Fix in Progress
Substation:
- Block Work Completed
- MEP 1st Fix Works Completed
1st Floor:
- 95% of Block Work Completed
- MEP 1st & 2nd Fix Works in Progress
2nd Floor:
- 97% of Block Work Completed
- MEP 1st Fix Works Under Progress
3rd & 4th Floor:
- 75% of Block Work Completed
5th Floor:
- De-Shuttering of 5th Floor, Pour 01 & 02 Completed
- 20% of Block Work Completed
6th Floor:
- Casting of 6th Floor Slab Pour 01 & 02 Completed
- 15% of Block Work Completed
Roof Floor:
- Casting of Slab 02 Completed
- 15% of Block Work Completed
- De-Shuttering in Progress
Swimming Pool:
- Structural Works Completed
- Plaster for Swimming Pool Completed
Facade:
- External Plaster from Ground to 1st Floor Completed
Launched
10th October 2022
Planned Handover
30th April 2024








Progress
31.35%
Stage
Ground Floor:
- Plaster Preparation and Plaster for Lobby and Staircase Completed
- Block Work, Ceiling Painting and Plaster Works in Progress
Substation:
- Casting of Trench Completed
- Block Work in Progress
1st Floor:
- De-Shuttering of 1st Floor Slab at Pour 03 Completed
1st to 3rd Floor:
- Block Work in Progress
4th Floor:
- Casting of 4th Floor Slab Pour 02 Completed
- Block Work in Progress
- De-Shuttering of 4th Floor Slab Pour 01 & 02 Completed
5th Floor:
- Casting and Vertical Works at 5th Floor Slab Pour 02 Completed
6th Floor:
- Casting of Verticals and Floor Slab at 6th Floor Pour 01 & 02 Completed
Roof Floor:
- Casting of Verticals and Floor Slab at Roof Pour 01 Completed
- Pour 02 in Progress
Launched
10th October 2022
Planned Handover
30th April 2024










Progress
23.22%
Stage
Underground:
- Tank Cleaning and Preparation of Tanks are in Progress
- Pump Room Plaster Preparation Completed and MEP 1st Fix Works in Progress
1st Floor:
- Casting of 1st Floor Slab Pour 03 Completed
- De-Shuttering of 1st Floor Slab at Pour 01 & 02 Completed
- Stressing & Patching for 1st Floor at Pour 01, 02 & 03 Completed
2nd Floor:
- Casting and De-Shuttering of 2nd Floor Slab Pour 02 Completed
3rd Floor:
- Casting and De-Shuttering of 3rd Floor Slab Pour 01 & 02 Completed
4th Floor:
- Casting of 4th Floor Slab Pour 01 Completed. Pour 02 is Partially Completed
- Stressing & Patching for 4th Floor at Pour 01 Completed and Pour 02 in Progress
5th Floor:
- Casting of 5th Floor Slab Pour 01 Completed. Vertical Works at 5th Floor Pour 02 in Progress
6th Floor:
- Casting of Verticals at 6th Floor Slab Pour 01 in Progress
- Scaffolding & Shuttering Works at 6th Floor at Pour 01 in Progress
Launched
10th October 2022
Planned Handover
30th April 2024





Progress
16.22%
Stage
Sub Structure:
- Water Proofing for Exposed Surface at Phase 03 Completed
- Backfilling at Phase 03 Completed
1st Floor:
- 100% of Stressing, Patching and Grouting for 1st Floor Slab at Pour 01 Area Completed
- 100% of Authority Inspection and Casting of 1st Floor Slab Pour 02 Completed
- 70% De-shuttering of 1st Floor Slab Pour 01 Area Completed
2nd Floor:
- 100% Verticals (Columns & Core Walls) 1st to 2nd Floor at Pour 01 Area Completed
- 100% of Authority Inspection and Casting of 2nd Floor Slab Pour 01 Completed
- 75% Verticals (Columns & Core Walls) 1st to 2nd Floor at Pour 02 Area Completed
3rd Floor:
- 100% of Scaffolding and Shuttering Works for 3rd Floor Slab Pour 01 Completed
- 50% of Authority Inspection and Casting of 3rd Floor Slab Pour 01 Completed
- 10% Verticals (Columns & Core Walls) 2nd to 3rd Floor at Pour 02 Area Completed
Launched
10th October 2022
Planned Handover
30th April 2024





Progress
10.50%
Stage
- 100% Vertical Columns & Core Walls at Pour Areas 1 to 3 Completed
- 100% Reinforcement, PT Works, Inspection and Casting of Pour Area 1 Completed
- De-watering at Water Tank & Pump Room in Phase 1 Area Completed
- Reinforcement, Formwork and Casting of Water Tank Top Slab Completed
- Backfilling at Phase 1 and 2 Area Completed
- Levelling, Anti-termite, PCC and Water Proofing below Raft at Phase 4 Completed
- Reinforcement, Formwork and Casting of Raft at Phase 4 Completed
Launched
10th October 2022
Planned Handover
30th April 2024






Progress
7.50%
Stage
- 100% of Reinforcement for Raft at Phase 2 Completed
- 100% of Form Work/Periphery Block Works for Raft Completed
- 100% of Casting of Raft at Phase 2 Completed
- 100% of Floor Beams at Phase 2 Completed
- 100% of Excavation Works at Phase 3 Completed
- 100% of Reinforcement for Footings at Phase 3 Completed
- 100% Water Proofing above PCC at Phase 2 Area Completed
- 90% Verticals (Columns & Core Walls) at Phase 2 Completed
Launched
10th October 2022
Planned Handover
30th April 2024









Progress
3.75%
Stage
- Mobilization Completed
- Excavation Works for Water Tank & Pump Room Area (Phase-1A) Completed
- Installation of De-Watering System at Water Tank Completed
- 100% of Excavation Works at Phase 2 Area Completed
- 100% of Levelling and Compaction at Phase 2 Area Completed
- 100% of Antitermite and PCC at Phase 2 Area Completed
- 100% Water Proofing above PCC at Phase 2 Area Completed
- 40% of Reinforcement for Raft at Phase 2 / Pour No.01 Completed
- 20% of Form Work/Periphery Block Works for Raft Completed
- 60% of Excavation Works at Phase 03 & 04 Area Completed
Launched
10th October 2022
Planned Handover
30th April 2024







Progress
1.01%
Stage
- 30% of Excavation Works for Water Tank & Pump Room Area (Phase-1A) Completed
- 80% of Excavation Works for Lift Pit Area (Phase-1B) Completed
- 30% of Excavation Works at Phase 2 Area Completed
Launched
10th October 2022
Planned Handover
30th April 2024