ZāZEN One
Jumeirah Village Triangle
100%
This project was delivered on time and handed over on January 31st 2022.
Timeline
Progress: | 100% |
Stage:
|
Final demarcation certificate obtained from Nakheel. |
Final demarcation certificate obtained from Trakhees. | |
DEWA power connection obtained. | |
DEWA approval for Solar panels and activation of meter completed. | |
DCD certificate obtained. | |
SIRA certificate obtained. | |
Final approved drawings from Trakhees received. | |
Nakheel Completion Certificate issued. | |
Nakheel stamped drawings received on 3rd January 2022. | |
Trakhees Completion Certificate received on 8th January 2022. | |
DCD inspection for LPG approved on 11th January 2022. | |
DEWA meters approved and received for all units on 20th January 2022. | |
DU inspection approved on January 22nd. | |
Dubai Land Department Building Completion Certificate received on 25th January 2022.
|
|
Building handover and snagging in process as of 26th January 2022. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 100% |
Stage:
|
Final demarcation certificate obtained from Nakheel. |
Final demarcation certificate obtained from Trakhees. | |
DEWA power connection obtained. | |
DEWA approval for Solar panels and activation of meter completed. | |
DCD certificate obtained. | |
SIRA certificate obtained. | |
Final approved drawings from Trakhees received. | |
Nakheel Completion Certificate issued. | |
Nakheel stamped drawings received on 3rd January 2022. | |
Trakhees Completion Certificate received on 8th January 2022. | |
DCD inspection for LPG approved on 11th January 2022. | |
DEWA meters approved and received for all units on 20th January 2022. | |
DU inspection approved on January 22nd. | |
Dubai Land Department Building Completion Certificate received on 25th January 2022.
|
|
Building handover and snagging in process as of 26th January 2022. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 92.80% |
Stage:
|
False ceiling work for the Ground Floor main entrance lobby completed. |
100% of MEP 3rd fix work from Ground to 7th Floor and Roof completed. | |
Facade work – 100% of aluminum & glazing work completed. | |
Facade work – 95% painting work completed. | |
100% of lift work completed. | |
100% of boundary wall work completed. | |
Front interlock & curb stone work at ground and podium floor completed. | |
Installation of way finding signage completed. | |
Swimming pool work completed. | |
Jogging track work completed. | |
Soil filling and irrigation work under progress. | |
Nakheel and Trakhees demarcation certificate obtained. | |
DEWA Water 1st inspection completed and comments incorporated. | |
DEWA Power obtained. | |
DU communication 1st inspection approved. | |
1st Dubai Civil Defense inspection completed and comments incorporated. | |
Solar Panel installation complete and 1st inspection approved. | |
75% of Lift installation and testing work completed. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 87.00% |
Stage:
|
MEP 2nd Fix work completed. |
Wardrobe work from Ground to 5th Floor completed. | |
Kitchen cabinet work from Ground Floor to 7th Floor completed. | |
Timber door work from Ground to 7th Floor and Roof completed. | |
Vanity work from Ground to 7th Floor completed. | |
False ceiling work from Gro und to 7th Floor and Roof completed. | |
Staircase handrail work at Ground and Podium Floor completed. | |
Balcony handrail from Podium to 7th Floor and Roof completed. | |
Facade work – 100% of External plastering work completed. | |
Facade work – 90% of Aluminium & Glazing work completed. | |
Facade work – 100% of Stone cladding work completed. | |
75% of Lift installation and testing work completed. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 81.09% |
Stage:
|
Wet area wall tile work and water proofing from Ground to 7th Floor completed. |
Wet area floor tiling from Ground to 7th Floor completed. | |
Dry tiling from Ground to 7th Floor completed. | |
1st coat painting work from Ground to 7th Floor completed. | |
Wardrobe installation from Ground to 5th Floor completed. | |
Kitchen cabinet installation from Ground to 5th Floor completed. | |
Timber door installation from Ground to 5th Floor completed. | |
Vanity counter installation from Ground to 2nd Floor completed. | |
MEP 1st and 2nd Fix work from Ground to Roof level completed. | |
False ceiling work from Ground to 4th Floor completed. | |
Balcony handrail installation from Podium to 3rd Floor completed. | |
90% of external plastering work completed. | |
85% of aluminium & glazing work completed. | |
80% of stone cladding work completed. | |
55% of lift installation completed. | |
55% of boundary wall completed. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 76.7% |
Stage:
|
Plaster work for all floors completed. |
Wet area wall tile work from 1st to 6th floor completed. | |
80% of wet area wall tile at 7th floor completed. | |
Wet area water proofing from 1st to 7th floor completed. | |
Wet area floor tiling from Ground to 7th floor completed. | |
95% of dry tiling from Ground to 4th floor completed. | |
90% of dry tiling on 5th & 6th floor completed. | |
Painting work from Ground to 7th floor under progress. | |
100% of wardrobe fixing on Ground & Podium floor completed. | |
90% of Kitchen cabinet work on Ground & Podium floor completed. | |
100% of Doors work on Ground & Podium floor completed. | |
100% of Vanity work on Ground & Podium floor completed. | |
MEP first fix work from 1st to 7th floor and Roof completed. | |
Façade work – External plastering under progress. | |
Façade work – Aluminum & glazing under progress. | |
Façade work – Stone cladding under progress. | |
Façade work – Painting under progress. | |
100% of Garbage chute work completed. | |
Lift work under progress. | |
Window cleaning system work under progress. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 66% |
Stage:
|
Plaster work at 5th & 6th Floor completed. |
Wet area wall tile work from 1st to 6th Floor completed. | |
Wet area floor tiling from Ground Floor to 3rd Floor completed. | |
Dry tiling from Ground Floor to 4th Floor completed. | |
Painting work from Ground Floor to 7th Floor under progress. | |
100% of Wardrobe work at the Ground and Podium Floor is completed. | |
100% of Doors work at Ground Podium Floor is completed. | |
100% of the Vanity work at the Ground and Podium Floor is completed. | |
MEP 1st Fix work from 1st to 7th Floor and Roof completed. | |
False Ceiling work from the Ground to 3rd Floor under progress. | |
Façade work – External plastering work under progress. | |
Façade work – Aluminum & Glazing work under progress. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 51% |
Stage:
|
Casting of parapet wall completed. |
Block work at Seventh and Roof floor completed. | |
Plaster work from Podium to 4th floor completed. | |
Wet area water proofing from 1st to 3rd floor completed. | |
Wet area floor and wall tiling from Ground floor to 3rd floor under progress. | |
MEP 1st Fix works from 1st to 3rd floor completed. | |
Facade external plastering works under progress. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 45% |
Stage:
|
Roof Floor and Top of Roof Slab casting completed. |
Parapet wall work under progress. | |
Block work on Second, Third and Fourth Floor completed. | |
Block work from Fifth to Seventh Floor under progress. | |
Plaster work at Podium, First and Second Floor completed. | |
Wet area water proofing from Ground to Second Floor under progress. | |
Wet area wall and floor tiling from Ground to Third Floor under progress. | |
Dry tiling from Ground to Second Floor under progress. | |
MEP 1st fix works at First Floor and Second Floor completed. | |
MEP 2nd fix works from Ground to Fourth Floor under progress. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 42% |
Stage:
|
Sixth Floor to Roof all the vertical elements completed. |
Seventh Floor slab casting completed. | |
Block work at Ground Floor, Podium Floor and First Floor completed. | |
Block work at Second Floor, Third Floor and Fourth Floor under progress. | |
MEP 1st fix work at Ground and Podium Floor completed. | |
MEP 1st fix work at First and Second Floor under progress. | |
MEP 2nd fix work at Ground Floor, Podium Floor and First Floor under progress. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 33.78% |
Stage:
|
Fifth Floor slab casting completed. |
Third to Sixth Floor all the vertical elements completed. | |
Block work at Ground Floor completed. | |
Block work at Podium Floor and First Floor under progress. | |
MEP works under progress at Ground Floor and Podium Floor. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 28.49% |
Stage:
|
2nd and 3rd floor slabs concreted. |
Block work in progress at Ground & Podium Floor. | |
Plastering work in progress at Ground Floor. | |
1st floor to 4th floor – all vertical elements concreted. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 24.19% |
Stage:
|
1st floor slab completed. |
1st floor to 2nd floor Column / Walls – 50% completed. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 22.04% |
Stage:
|
Casting of Podium floor completed. |
50% C asting of 1st floor completed. | |
Duplex Area – Cover slab concreted. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 14.05% |
Stage:
|
Casting of Grade slab completed. |
Casting of Ramp to Podium floor completed. | |
Ground Floor – Column / Walls concreting completed. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 12.71% |
Stage:
|
Underground services for Drainage completed. |
Back Filling below the Grade slab completed. | |
Grade slab in progress. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 9.82% |
Stage:
|
All the Foundations concreted. |
Neck Column & Tie beam works completed. | |
Substructure waterproofing completed. | |
Backfilling up to Tie beam level completed. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 2.25% |
Stage:
|
Excavation completed. |
Casting of major areas – Raft & Foundations completed. | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |
Progress: | 0.08% |
Stage:
|
Mobilization completed |
Excavation in progress | |
Launched: | 15th January 2020 |
Planned Handover: | January 2022 |