ZāZEN One

Jumeirah Village Triangle

100%

This project was delivered on time and handed over on January 31st 2022.

Timeline

Progress: 100%
Stage:
Final demarcation certificate obtained from Nakheel.
Final demarcation certificate obtained from Trakhees.
DEWA power connection obtained.
DEWA approval for Solar panels and activation of meter completed.
DCD certificate obtained.
SIRA certificate obtained.
Final approved drawings from Trakhees received.
Nakheel Completion Certificate issued.
Nakheel stamped drawings received on 3rd January 2022.
Trakhees Completion Certificate received on 8th January 2022.
DCD inspection for LPG approved on 11th January 2022.
DEWA meters approved and received for all units on 20th January 2022.
DU inspection approved on January 22nd.
Dubai Land Department Building Completion Certificate received on 25th January 2022.
Building handover and snagging in process as of 26th January 2022.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 100%
Stage:
Final demarcation certificate obtained from Nakheel.
Final demarcation certificate obtained from Trakhees.
DEWA power connection obtained.
DEWA approval for Solar panels and activation of meter completed.
DCD certificate obtained.
SIRA certificate obtained.
Final approved drawings from Trakhees received.
Nakheel Completion Certificate issued.
Nakheel stamped drawings received on 3rd January 2022.
Trakhees Completion Certificate received on 8th January 2022.
DCD inspection for LPG approved on 11th January 2022.
DEWA meters approved and received for all units on 20th January 2022.
DU inspection approved on January 22nd.
Dubai Land Department Building Completion Certificate received on 25th January 2022.
Building handover and snagging in process as of 26th January 2022.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 92.80%
Stage:
False ceiling work for the Ground Floor main entrance lobby completed.
100% of MEP 3rd fix work from Ground to 7th Floor and Roof completed.
Facade work – 100% of aluminum & glazing work completed.
Facade work – 95% painting work completed.
100% of lift work completed.
100% of boundary wall work completed.
Front interlock & curb stone work at ground and podium floor completed.
Installation of way finding signage completed.
Swimming pool work completed.
Jogging track work completed.
Soil filling and irrigation work under progress.
Nakheel and Trakhees demarcation certificate obtained.
DEWA Water 1st inspection completed and comments incorporated.
DEWA Power obtained.
DU communication 1st inspection approved.
1st Dubai Civil Defense inspection completed and comments incorporated.
Solar Panel installation complete and 1st inspection approved.
75% of Lift installation and testing work completed.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 87.00%
Stage:
MEP 2nd Fix work completed.
Wardrobe work from Ground to 5th Floor completed.
Kitchen cabinet work from Ground Floor to 7th Floor completed.
Timber door work from Ground to 7th Floor and Roof completed.
Vanity work from Ground to 7th Floor completed.
False ceiling work from Gro und to 7th Floor and Roof completed.
Staircase handrail work at Ground and Podium Floor completed.
Balcony handrail from Podium to 7th Floor and Roof completed.
Facade work – 100% of External plastering work completed.
Facade work – 90% of Aluminium & Glazing work completed.
Facade work – 100% of Stone cladding work completed.
75% of Lift installation and testing work completed.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 81.09%
Stage:
Wet area wall tile work and water proofing from Ground to 7th Floor completed.
Wet area floor tiling from Ground to 7th Floor completed.
Dry tiling from Ground to 7th Floor completed.
1st coat painting work from Ground to 7th Floor completed.
Wardrobe installation from Ground to 5th Floor completed.
Kitchen cabinet installation from Ground to 5th Floor completed.
Timber door installation from Ground to 5th Floor completed.
Vanity counter installation from Ground to 2nd Floor completed.
MEP 1st and 2nd Fix work from Ground to Roof level completed.
False ceiling work from Ground to 4th Floor completed.
Balcony handrail installation from Podium to 3rd Floor completed.
90% of external plastering work completed.
85% of aluminium & glazing work completed.
80% of stone cladding work completed.
55% of lift installation completed.
55% of boundary wall completed.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 76.7%
Stage:
Plaster work for all floors completed.
Wet area wall tile work from 1st to 6th floor completed.
80% of wet area wall tile at 7th floor completed.
Wet area water proofing from 1st to 7th floor completed.
Wet area floor tiling from Ground to 7th floor completed.
95% of dry tiling from Ground to 4th floor completed.
90% of dry tiling on 5th & 6th floor completed.
Painting work from Ground to 7th floor under progress.
100% of wardrobe fixing on Ground & Podium floor completed.
90% of Kitchen cabinet work on Ground & Podium floor completed.
100% of Doors work on Ground & Podium floor completed.
100% of Vanity work on Ground & Podium floor completed.
MEP first fix work from 1st to 7th floor and Roof completed.
Façade work – External plastering under progress.
Façade work – Aluminum & glazing under progress.
Façade work – Stone cladding under progress.
Façade work – Painting under progress.
100% of Garbage chute work completed.
Lift work under progress.
Window cleaning system work under progress.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 66%
Stage:
Plaster work at 5th & 6th Floor completed.
Wet area wall tile work from 1st to 6th Floor completed.
Wet area floor tiling from Ground Floor to 3rd Floor completed.
Dry tiling from Ground Floor to 4th Floor completed.
Painting work from Ground Floor to 7th Floor under progress.
100% of Wardrobe work at the Ground and Podium Floor is completed.
100% of Doors work at Ground Podium Floor is completed.
100% of the Vanity work at the Ground and Podium Floor is completed.
MEP 1st Fix work from 1st to 7th Floor and Roof completed.
False Ceiling work from the Ground to 3rd Floor under progress.
Façade work – External plastering work under progress.
Façade work – Aluminum & Glazing work under progress.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 51%
Stage:
Casting of parapet wall completed.
Block work at Seventh and Roof floor completed.
Plaster work from Podium to 4th floor completed.
Wet area water proofing from 1st to 3rd floor completed.
Wet area floor and wall tiling from Ground floor to 3rd floor under progress.
MEP 1st Fix works from 1st to 3rd floor completed.
Facade external plastering works under progress.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 45%
Stage:
Roof Floor and Top of Roof Slab casting completed.
Parapet wall work under progress.
Block work on Second, Third and Fourth Floor completed.
Block work from Fifth to Seventh Floor under progress.
Plaster work at Podium, First and Second Floor completed.
Wet area water proofing from Ground to Second Floor under progress.
Wet area wall and floor tiling from Ground to Third Floor under progress.
Dry tiling from Ground to Second Floor under progress.
MEP 1st fix works at First Floor and Second Floor completed.
MEP 2nd fix works from Ground to Fourth Floor under progress.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 42%
Stage:
Sixth Floor to Roof all the vertical elements completed.
Seventh Floor slab casting completed.
Block work at Ground Floor, Podium Floor and First Floor completed.
Block work at Second Floor, Third Floor and Fourth Floor under progress.
MEP 1st fix work at Ground and Podium Floor completed.
MEP 1st fix work at First and Second Floor under progress.
MEP 2nd fix work at Ground Floor, Podium Floor and First Floor under progress.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 33.78%
Stage:
Fifth Floor slab casting completed.
Third to Sixth Floor all the vertical elements completed.
Block work at Ground Floor completed.
Block work at Podium Floor and First Floor under progress.
MEP works under progress at Ground Floor and Podium Floor.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 28.49%
Stage:
2nd and 3rd floor slabs concreted.
Block work in progress at Ground & Podium Floor.
Plastering work in progress at Ground Floor.
1st floor to 4th floor – all vertical elements concreted.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 24.19%
Stage:
1st floor slab completed.
1st floor to 2nd floor Column / Walls – 50% completed.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 22.04%
Stage:
Casting of Podium floor completed.
50% C asting of 1st floor completed.
Duplex Area – Cover slab concreted.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 14.05%
Stage:
Casting of Grade slab completed.
Casting of Ramp to Podium floor completed.
Ground Floor – Column / Walls concreting completed.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 12.71%
Stage:
Underground services for Drainage completed.
Back Filling below the Grade slab completed.
Grade slab in progress.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 9.82%
Stage:
All the Foundations concreted.
Neck Column & Tie beam works completed.
Substructure waterproofing completed.
Backfilling up to Tie beam level completed.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 2.25%
Stage:
Excavation completed.
Casting of major areas – Raft & Foundations completed.
Launched: 15th January 2020
Planned Handover: January 2022
Progress: 0.08%
Stage:
Mobilization completed
Excavation in progress
Launched: 15th January 2020
Planned Handover: January 2022