Zazen One Construction Updates

100% Complete

ZāZEN One

CONSTRUCTION UPDATES
Start Date

Jan 2020

Completion Date

Jan 2022

Jumeirah Village Triangle

This project was delivered on time and handed over on January 31st 2022.

TIMELINE

ZāZEN ONE – CONSTRUCTION UPDATE

Progress

100%

Stage

Authority Inspection & Approvals:
  • Final demarcation certificate obtained from Nakheel
  • Final demarcation certificate obtained from Trakhees
  • DCD certificate obtained
  • SIRA certificate obtained
  • DCD inspection for LPG approved on 11th January 2022
  • Dubai Land Department Building Completion Certificate received on 25th January 2022
Utilities & Services:
  • DEWA power connection obtained
  • DEWA meters approved and received for all units on 20th January 2022
  • DEWA approval for solar panels and activation of meter completed
  • DU inspection approved on 22nd January 2022
Approvals & Documentation:
  • Final approved drawings from Trakhees received
  • Nakheel stamped drawings received on 3rd January 2022
  • Trakhees Completion Certificate received on 8th January 2022
  • Nakheel Completion Certificate issued
Project Completion & Handover:
  • Building handover and snagging in process as of 26th January 2022

Launched

15th January 2020

Planned Handover

January 2022

Progress

100%

Stage

Authority Inspection & Approvals:
  • Final demarcation certificate obtained from Nakheel
  • Final demarcation certificate obtained from Trakhees
  • DCD certificate obtained
  • SIRA certificate obtained
  • DCD inspection for LPG approved on 11th January 2022
  • Dubai Land Department Building Completion Certificate received on 25th January 2022
Utilities & Services:
  • DEWA power connection obtained
  • DEWA approval for Solar panels and activation of meter completed
  • DEWA meters approved and received for all units on 20th January 2022
  • DU inspection approved on 22nd January 2022
Documentation & Completion:
  • Final approved drawings from Trakhees received
  • Nakheel stamped drawings received on 3rd January 2022
  • Trakhees Completion Certificate received on 8th January 2022
  • Nakheel Completion Certificate issued
  • Building handover and snagging in process as of 26th January 2022

Launched

15th January 2020

Planned Handover

January 2022

Progress

92.80%

Stage

Construction & Finishing Works:
  • False ceiling work for the Ground Floor main entrance lobby completed
  • 100% of MEP 3rd fix work from Ground to 7th Floor and Roof completed
  • Facade work – 100% of aluminum & glazing work completed
  • Facade work – 95% painting work completed
  • 100% of lift work completed
  • 100% of boundary wall work completed
  • Front interlock & curb stone work at ground and podium floor completed
  • Installation of way finding signage completed
  • Swimming pool work completed
  • Jogging track work completed
  • Soil filling and irrigation work under progress
Authority Inspection & Approvals:
  • Nakheel and Trakhees demarcation certificate obtained
  • DEWA Water 1st inspection completed and comments incorporated
  • DEWA Power obtained
  • DU communication 1st inspection approved
  • 1st Dubai Civil Defense inspection completed and comments incorporated
  • Solar Panel installation complete and 1st inspection approved
  • 75% of lift installation and testing work completed

Launched

15th January 2020

Planned Handover

January 2022

Progress

87.00%

Stage

Interior & Finishing Works:
  • MEP 2nd Fix work completed
  • Wardrobe work from Ground to 5th Floor completed
  • Kitchen cabinet work from Ground Floor to 7th Floor completed
  • Timber door work from Ground to 7th Floor and Roof completed
  • Vanity work from Ground to 7th Floor completed
  • False ceiling work from Ground to 7th Floor and Roof completed
  • Staircase handrail work at Ground and Podium Floor completed
  • Balcony handrail from Podium to 7th Floor and Roof completed
Facade & External Works:
  • Facade work – 100% of external plastering work completed
  • Facade work – 90% of aluminium & glazing work completed
  • Facade work – 100% of stone cladding work completed
  • 75% of lift installation and testing work completed

Launched

15th January 2020

Planned Handover

January 2022

Progress

81.09%

Stage

Interior Works:
  • Wet area wall tile work and waterproofing from Ground to 7th Floor completed
  • Wet area floor tiling from Ground to 7th Floor completed
  • Dry tiling from Ground to 7th Floor completed
  • 1st coat painting work from Ground to 7th Floor completed
  • Wardrobe installation from Ground to 5th Floor completed
  • Kitchen cabinet installation from Ground to 5th Floor completed
  • Timber door installation from Ground to 5th Floor completed
  • Vanity counter installation from Ground to 2nd Floor completed
  • MEP 1st and 2nd Fix work from Ground to Roof level completed
  • False ceiling work from Ground to 4th Floor completed
  • Balcony handrail installation from Podium to 3rd Floor completed
Facade & External Works:
  • 90% of external plastering work completed
  • 85% of aluminium & glazing work completed
  • 80% of stone cladding work completed
  • 55% of lift installation completed
  • 55% of boundary wall completed

Launched

15th January 2020

Planned Handover

January 2022

Progress

76.7%

Stage

Interior & Finishing Works:
  • Plaster work for all floors completed
  • Wet area wall tile work from 1st to 6th floor completed
  • 80% of wet area wall tile at 7th floor completed
  • Wet area waterproofing from 1st to 7th floor completed
  • Wet area floor tiling from Ground to 7th floor completed
  • 95% of dry tiling from Ground to 4th floor completed
  • 90% of dry tiling on 5th & 6th floor completed
  • Painting work from Ground to 7th floor under progress
  • 100% of wardrobe fixing on Ground & Podium floor completed
  • 90% of kitchen cabinet work on Ground & Podium floor completed
  • 100% of doors work on Ground & Podium floor completed
  • 100% of vanity work on Ground & Podium floor completed
  • MEP first fix work from 1st to 7th floor and Roof completed
Facade & External Works:
  • Façade work – external plastering under progress
  • Façade work – aluminum & glazing under progress
  • Façade work – stone cladding under progress
  • Façade work – painting under progress
  • 100% of garbage chute work completed
  • Lift work under progress
  • Window cleaning system work under progress

Launched

15th January 2020

Planned Handover

January 2022

Progress

66%

Stage

Interior Works:
  • Plaster work at 5th & 6th Floor completed
  • Wet area wall tile work from 1st to 6th Floor completed
  • Wet area floor tiling from Ground Floor to 3rd Floor completed
  • Dry tiling from Ground Floor to 4th Floor completed
  • Painting work from Ground Floor to 7th Floor under progress
  • 100% of wardrobe work at the Ground and Podium Floor completed
  • 100% of doors work at the Ground and Podium Floor completed
  • 100% of vanity work at the Ground and Podium Floor completed
  • MEP 1st Fix work from 1st to 7th Floor and Roof completed
  • False ceiling work from the Ground to 3rd Floor under progress
Facade & External Works:
  • Façade work – external plastering work under progress
  • Façade work – aluminum & glazing work under progress

Launched

15th January 2020

Planned Handover

January 2022

Progress

51%

Stage

Structural & Interior Works:
  • Casting of parapet wall completed
  • Block work at Seventh and Roof floor completed
  • Plaster work from Podium to 4th floor completed
  • Wet area waterproofing from 1st to 3rd floor completed
  • Wet area floor and wall tiling from Ground floor to 3rd floor under progress
  • MEP 1st Fix works from 1st to 3rd floor completed
Facade Works:
  • Facade external plastering works under progress

Launched

15th January 2020

Planned Handover

January 2022

Progress

45%

Stage

Structural Works:
  • Roof Floor and Top of Roof Slab casting completed
  • Parapet wall work under progress
  • Block work on Second, Third and Fourth Floor completed
  • Block work from Fifth to Seventh Floor under progress
Interior & MEP Works:
  • Plaster work at Podium, First and Second Floor completed
  • Wet area waterproofing from Ground to Second Floor under progress
  • Wet area wall and floor tiling from Ground to Third Floor under progress
  • Dry tiling from Ground to Second Floor under progress
  • MEP 1st fix works at First Floor and Second Floor completed
  • MEP 2nd fix works from Ground to Fourth Floor under progress

Launched

15th January 2020

Planned Handover

January 2022

Progress

42%

Stage

Structural Works:
  • Sixth Floor to Roof all the vertical elements completed
  • Seventh Floor slab casting completed
  • Block work at Ground Floor, Podium Floor and First Floor completed
  • Block work at Second Floor, Third Floor and Fourth Floor under progress
MEP Works:
  • MEP 1st fix work at Ground and Podium Floor completed
  • MEP 1st fix work at First and Second Floor under progress
  • MEP 2nd fix work at Ground Floor, Podium Floor and First Floor under progress

Launched

15th January 2020

Planned Handover

January 2022

Progress

33.78%

Stage

Structural Works:
  • Fifth Floor slab casting completed
  • Third to Sixth Floor all the vertical elements completed
  • Block work at Ground Floor completed
  • Block work at Podium Floor and First Floor under progress
MEP Works:
  • MEP works under progress at Ground Floor and Podium Floor

Launched

15th January 2020

Planned Handover

January 2022

Progress

28.49%

Stage

Structural Works:
  • 2nd and 3rd floor slabs concreted
  • 1st floor to 4th floor – all vertical elements concreted
Interior & Block Works:
  • Block work in progress at Ground & Podium Floor
  • Plastering work in progress at Ground Floor

Launched

15th January 2020

Planned Handover

January 2022

Progress

24.19%

Stage

Structural Works:
  • 1st floor slab completed
  • 1st floor to 2nd floor Column / Walls – 50% completed

Launched

15th January 2020

Planned Handover

January 2022

Progress

22.04%

Stage

Structural Works:
  • Casting of Podium floor completed
  • 50% Casting of 1st floor completed
  • Duplex Area – Cover slab concreted

Launched

15th January 2020

Planned Handover

January 2022

Progress

14.05%

Stage

Structural Works:
  • Casting of Grade slab completed
  • Casting of Ramp to Podium floor completed
  • Ground Floor – Column / Walls concreting completed

Launched

15th January 2020

Planned Handover

January 2022

Progress

12.71%

Stage

Underground & Foundation Works:
  • Underground services for Drainage completed
  • Back Filling below the Grade slab completed
  • Grade slab in progress

Launched

15th January 2020

Planned Handover

January 2022

Progress

9.82%

Stage

Foundation & Substructure Works:
  • All the Foundations concreted
  • Neck Column & Tie beam works completed
  • Substructure waterproofing completed
  • Backfilling up to Tie beam level completed

Launched

15th January 2020

Planned Handover

January 2022

Progress

2.25%

Stage

Excavation & Foundation Works:
  • Excavation completed
  • Casting of major areas – Raft & Foundations completed

Launched

15th January 2020

Planned Handover

January 2022

Progress

0.08%

Stage

Initial Works:
  • Mobilization completed
  • Excavation in progress

Launched

15th January 2020

Planned Handover

January 2022