ZāZEN IVY – Construction Update

Al Furjan

60.2%

It is currently under construction and due for completion in March 2026.

This project is registered under RERA project number 3109.

Timeline

Progress: 60.20%
Stage: Ground Floor:
· Structure Works· Finishing Works
– Ceiling Paint preparation Works, 70% completed- Wall Plaster Works, 90% completed – Epoxy Flooring for Pump Room, 100% Completed – GRP for Water Tank, 100% Completed- FIC Manhole GRP Work, 100% Completed
· MEP Works
– H/L MEP Works, 45%- Fire Pump installed, 100% Completed- Transfer Pump installed, 100% Completed

1st Floor:
· Structure Works
– Swimming Pool Deck Slab & Walls, 100% Completed
· Finishing Works
– Wall & Floor Tile Works in Apartment, 98% completed – Floor Tile Works in Corridor, 98% completed- Aluminium Works, framing 93% Completed / Glassing 75% completed- Vanity counters, 85 % Completed- Wardrobe fixed, 85% completed – Gypsum board Closure 100 % completed- Paint preparation Works, 95% Completed
· MEP Works: 95% Completed

2nd Floor:
· Finishing Works
– Wall Tile Works, 100 % Completed- Floor Tile Works, 100 % completed – Aluminium Works: Framing 40% Completed – False Ceiling: Framing Works 100% Completed- Gypsum board Closure, 60 % completed – Vanity counters, 50 % Completed- Wardrobe fixed, 50% completed – Paint preparation Works, 95% Completed
· MEP Works
– MEP H/L, 95% Completed

3rd Floor:
· Finishing Works
– Waterproofing Wet Area, 100% Completed- Floor Tile Works, 100% completed – Wall Tile Works, 100 % Completed- Paint preparation Works, 90% Completed
· MEP Works
– MEP H/L, 75% Completed

4th Floor
· Finishing Works
– Wall Plaster Works, 95% Completed – Waterproofing Wet Area, 100% Completed- Ceiling Anti-fungus wet area paint, 100% Completed – Wall Tile Works, 15 % Completed- Floor Tile Works, 70 % completed
· MEP Works
– MEP H/L, 35% Completed – MEP 1st Fix Works, 100 % Completed

5th Floor
· Finishing Works
– Block Works, 100 % Completed – Wall Plaster Works, 35% Completed – Ceiling Anti-fungus wet area paint, 100% Completed
· MEP Works
– MEP H/L, 25 % Completed – MEP 1st Fix Works, 85 % Completed

6th Floor
· Finishing Works
– Block Works, 100 % Completed – Wall Plaster Works, 15% Completed

Roof Floor
· Structure Works
– Aluminium Pergola Foundation Casted, 100% Completed
· Finishing Works
– Parapet Plaster Works, 100% Completed- Combo System work – foam 100 completed, screed 65% completed
· MEP Works
– MEP 1st Fix Works, 100 % Completed FAHU Delivered 100%

Top Roof Floor
· Structure Works
– Combo System Works: Foam, 00% Completed
External Elevation Finishing Works
– Elevation 1 Plaster Works, 100% Completed – Elevation 2 Plaster Works, 20% Completed – Elevation 3 Plaster Works, 45% Completed – Elevation 4 Plaster Works, 40% Completed – Elevation 1 primer Works, 100% Completed – Elevation 2 primer Works, 10% Completed – Elevation 4 primer Works, 30% Completed – Balcony Aluminium U-Channel Installation, 100% Completed
Internal Finishing Works
· Lift Works
– Lift Pit Waterproofing, 100% Completed – Elevators work 10% completed

Launched: 15th July 2024
Planned Handover: 30th March 2026

Progress:

45.30%

Stage:

Ground Floor:

  • SOG preparation (Part 2), 98% completed
  • Ceiling Paint preparation Works, 60% completed
  • Wall Plaster Works, 90% completed
  • Main Lobby Block Works, 100% completed
  • Generator Room Block Works, 100% completed
  • Epoxy Flooring for Pump Room, 90% completed
  • GRP for Water Tank (Preparation work started, GRP Materials fully delivered)
  • FIC Manhole GRP Work, 60% completed
  • H/L MEP Works, 40% completed
  • Fire Pump Set Delivered
  • Transfer Pump Delivered

1st Floor:

  • Swimming Pool Flooring Casted, 100% completed
  • Swimming Pool Deck Slab & Wall Shuttering Works ongoing
  • Wall & Floor Tile Works in Apartment, 95% completed
  • Floor Tile Works in Corridor, 95% completed
  • Aluminum Framing Works, 90% completed
  • Glass Delivered
  • Timber Doors, 100% Delivered
  • Subframes, 100% completed
  • Kitchen Cabinet and Wardrobe, 100% delivered
  • Vanity counters, 100% material delivered
  • False Ceiling Framing Works, 100% completed / Gypsum board Closure, 10% completed
  • Paint preparation Works, 90% completed
  • MEP H/L, 90% completed

2nd Floor:

  • Wall Tile Works, 70% completed
  • Floor Tile Works, 80% completed
  • Aluminum Framing works, 20% completed
  • Timber Doors, 90% delivered | Subframes, 100% completed
  • False Ceiling Framing Works, 75% completed
  • Paint preparation Works, 90% completed
  • MEP H/L, 90% completed

3rd Floor:

  • Waterproofing Wet Area, 90% completed
  • Floor Tile Works, 70% completed
  • Subframes Joinery work, 100% completed
  • Paint preparation Works, 50% completed
  • MEP H/L, 50% completed

4th Floor:

  • Wall Plaster Works, 30% completed
  • Ceiling Antifungus wet area paint, 90% completed
  • MEP H/L, 25% completed
  • MEP 1st Fix Works, 85% completed

5th Floor:

  • Deshuttering of 6th Floor Slab, 100% completed
  • Block Works, 75% completed
  • Ceiling Antifungus wet area paint, 90% completed
  • MEP H/L, 15% completed
  • MEP 1st Fix Works, 10% completed

6th Floor:

  • Deshuttering of Roof Floor Slab, 100% completed
  • Block Works, 30% completed

Roof Floor:

  • Deshuttering of Top Roof Floor Slab, 100% completed
  • MEP Foundation Casted, 100% completed
  • Aluminum Pergola Foundation Casted, 100% completed
  • Parapet Block Works, 100% completed
  • Parapet Plaster Works, 60% completed
  • Preparation for Combo System Works, 60% completed
  • Floor Piping for Roof Floor
  • MEP 1st Fix Works, 70% completed

Top Roof Floor:

  • Top Roof Floor Slab Casted, 100% completed
  • Lift Slab Casted, 100% completed
  • Top Roof Parapet Casted, 100% completed
  • Preparation for Combo System Works, 10% completed

External Elevation Finishing Works:

  • Elevation 1 Plaster Works, 20% completed
  • Balcony Aluminum U-Channel Installation, 25% completed

Internal Finishing Works:

  • Lift Pit Waterproofing, 100% completed
  • All Elevators Materials, 100% delivered

Launched:

15th July 2024

Planned Handover:

30th March 2026

Progress:

40.70%

Stage:

Ground Floor:

  • SOG preparation (PART 2), 90% completed.
  • Ceiling paint preparation, 20% completed.
  • Plaster work, 90% completed.

 

1st Floor:

  • MEP 3rd Fix, 5% completed.
  • Ceiling and wall Paint preparation, 90% completed.
  • Ceiling Suspension works, 90% completed.
  • Walls and floors tiles installation, 90% completed.
  • Water proofing works, 100% completed.

2nd Floor:

  • Blockwork, 100% completed.
  • Plaster works, 100% completed.
  • MEP 2nd Fix, 100% completed.
  • Ceiling and wall Paint preparation, 90% completed.
  • Water proofing works, 80% completed
  • Walls and floors tiles installation, 40% completed.

 

3rd Floor:

  • Block works, 100% completed.
  • Plaster works, 100% completed.
  • MEP 2nd Fix, 75% completed.
  • Ceiling and wall Paint preparation, 15% completed.

 

4th Floor

  • Block works, 80% completed.
  • MEP 1st Fix, 20% completed.

 

5th Floor

  • Block works, 15% completed.

 

6th Floor

  • De-shuttering works, 10% completed.

 

Roof Floor

  • Reinforcement work for slab, 100% completed.
  • PT work for slab, 100% completed.
  • MEP work for slab, 100% completed.
  • Authority Inspection for casting, 100% completed.
  • Slab concrete casting, 100% completed.
  • Block works, 50% completed.

 

Top Roof Floor

  • Reinforcement work for slab, 100% completed.
  • MEP work for slab, 100% completed.
  • Authority Inspection for casting, 100% completed.
  • Slab concrete casting, 100% completed.

 

Facade

  • External plaster preparation works, 10% completed.

Launched:

15th July 2024

Planned Handover:

30th March 2026

Progress:

38.31%

Stage

Ground Floor:

Substation DEWA IR, 100% completed.

SOG preparation (PART 1), 100% completed.

SOG preparation (PART 2), 10% completed.

De-shuttering (PART 2), 100% completed.

Plaster works, 60% completed.

1st Floor:

Plaster works, 100% completed.

Dry area tile installation, 60% completed.

Water proofing works, 30% completed.

MEP 2nd Fix, 100% completed.

Ceiling and wall Paint preparation, 60% completed.

2nd Floor:

Block works, 100% completed.

Plaster works, 75% completed.

MEP 2nd Fix, 25% completed.

3rd Floor:

Block works, 60% completed.

 4th Floor:

De-shuttering, 100% completed.

Block works, 10% completed.

 6th Floor:

Stressing & Patching for slab, 100% completed.

Column and Wall casting, 100% completed.

 Roof Floor:

Reinforcement work for slab, 90% completed.

PT work for slab, 90% completed.

MEP work for slab, 90% completed.

Launched:

15th July 2024

Planned Handover:

30th March 2026

Progress:

32.40%

Stage:

Ground Floor:

Substation & LV room block works, 100% completed.
Substation aluminium door, 100% completed.
SOG preparation (PART 1), 75% completed.
External block work, 40% completed.
De-shuttering (PART 2), 50% completed.

1st Floor:

Block work, 100% completed.
Plaster work, 50% completed.
MEP 2nd Fix, 90% completed.
Ceiling Paint & Preparation, 30% completed.
Tiling works, 5% completed.

 

2nd Floor:

Blockwork, 90% completed.
Plaster works, 10% completed.
MEP 2nd Fix, 15% completed.

3rd Floor:

De-shuttering, 90% completed.
Block works, 30% completed.

5th Floor:

Reinforcement work for slab, 100% completed.
PT work for slab, 100% completed.
MEP work for slab, 100% completed.
Slab concrete casting, 100% completed.
Authority Inspection for casting, 100% completed.
Stressing & Patching for slab, 100% completed.
Column and Wall casting, 100% completed. 

6th Floor:

Reinforcement work for slab, 100% completed.
PT work for slab, 100% completed.
MEP work for slab, 100% completed.
Authority Inspection for casting, 100% completed.
Slab concrete casting, 100% completed.

Launched:

15th July 2024

Planned Handover:

30th March 2026

Progress:

30.25%

Stage:

Ground Floor

  • Substation, LV room block works, 100% completed
  • De-shuttering (PART 1) – 100 % completed
  • SOG preparation (PART 1) – 75% completed
  • External blockwork – 40% completed

1st Floor:

  • Blockwork, 95% completed.
  • Plaster work, 15% completed.
  • MEP 2nd Fix, 40% completed.

2nd Floor:

  • Blockwork, 15% completed.
  • De-shuttering work, 100% completed.

3rd Floor:

  • Column and Wall casting for 3rd Floor slab, 100% completed.
  • Column and Wall De-shuttering & Curing.

4th Floor

  • Reinforcement work for slab, 100% completed.
  • PT work for slab, 100% completed.
  • MEP work for slab, 100% completed.
  • Authority Inspection for casting, 100% completed.
  • Slab concrete casting, 100% completed.
  • Stressing & Patching for slab, 100% completed.
  • Column and Wall casting, 100% completed.
  • Column and Wall De-shuttering & Curing. 

5th Floor

  • Reinforcement work for slab, 30% completed.
  • PT work for slab, 15% completed.

Launched:

15th July 2024

Planned Handover:

30th March 2026

Progress:

26.10%

Stage:

Ground Floor

  • Substation, LV room block works, 50% completed.
  • De-shuttering (PART 1) – 80% completed.
  • SOG preparation (PART 1) – 80% completed.

 

1st Floor:

  • Blockwork lay out, 35% completed.
  • Blockworks, 10% completed.
  • De-Shuttering work, 100% completed.

2nd Floor:

  • Reinforcement work for slab, 100% completed.
  • PT work for slab, 100% completed.
  • Authority Inspection for casting, 100% completed.
  • Slab concrete casting, 100% completed.
  • MEP works for the slab, 100% completed.
  • Stressing & Patching for 2nd Floor slab, 100% completed.
  • Column and Wall casting on 2nd Floor slab, 100% completed.
  • Column and Wall De-shuttering & Curing

3rd Floor:

  • Reinforcement work for slab, 100% completed.
  • PT work for slab, 100% completed.
  • Authority Inspection for casting slab, 100% completed.
  • Slab concrete casting, 97% completed.
  • MEP works for the slab, 100% completed.
  • Column and Wall casting on 3rd Floor slab, 20% completed.
  • Column and Wall De-shuttering & Curing 20% completed.

Launched:

15th July 2024

Planned Handover:

30th March 2026

Progress:

24.75%

Stage:

1st Floor:

Reinforcement work for slab, 100% completed.
PT work for slab, 100% completed.
Authority Inspection for casting, 100% completed.
Slab concrete casting, 100% completed. MEP works, 100% completed.
Stressing & Patching for 1st Floor slab, 100% completed.

2nd Floor:

Column and Wall casting for 2nd Floor slab, 100% completed.
Reinforcement work for slab, 100% completed.
PT work for slab, 100% completed.
Authority Inspection for casting, 100% completed.
Slab concrete casting, 100% completed.
MEP works, 100% completed. Stressing & Patching for 2nd Floor slab, 50% completed.

3rd Floor:

Vertical columns steel reinforcement, 10% completed.

Launched: 15th July 2024
Planned Handover: 30th March 2026

Progress:

20.85%

Stage:

Main Raft & Foundation:

Raft & isolated footing casting, 100% completed.
Casting of Tie beams, 100% completed.
Road base & Screed under Grade Slab (SOG), 100% completed.
MEP services under SOG, 70% completed.
Ground floor columns and core walls, 100% completed.
1st floor slab shuttering, 95% completed.
1st floor slab Steel and PT works, 95% completed.
1st floor slab MEP works, 85% completed.

Launched: 15th July 2024
Planned Handover: 30th March 2026

Progress:

16.45%

Stage:

Main Raft & Foundation:

Raft & isolated footing casting, 100% completed.
Casting of Tie beams, 95% completed.
Road base & Screed under Grade Slab (SOG), 80% completed.
MEP services under SOG, 60% completed.
Ground floor columns and core walls, 60% completed.
1st floor slab shuttering, 40% completed.
Tower Crane Setup and Operations, 100% completed.

Launched: 15th July 2024
Planned Handover: 30th March 2026

Progress:

13.49%

Stage:

Main Raft & Foundation:

2nd phase Waterproofing for Main Raft top, Zone 1, 100% completed.
2 layers of Back Filling & Solid Block for Substructure, Zone 1, 100% completed.
Casting Slab of Water Tank, Pump Rooms and Staircase, Zone 1, 100% completed.
Water Proofing Slab of Water Tank, Pump Rooms, Zone 1, 100% completed.
Casting Tie Beam and Water Proofing, Zone 1, 75% completed.
Road Base & Screed under Grade Slab, Zone 1, 25% completed.
MEP services under Grade Slab, Zone 1, 60% completed.
Excavation of Isolated footing, Road base & PCC, Zone 2, 75% completed.
Casting Isolated footing & Neck Columns, Zone 2, 50% completed.
Waterproofing Isolated footing & Neck Columns, Zone 2, 45% completed.
Casting Tower Crane Foundation, Zone 2, 100% completed.

Launched: 15th July 2024
Planned Handover: 30th March 2026

Progress:

9.12%

Stage:

Main Raft:

Reinforcement for main raft, lift pit and substation completed.
Main Raft concrete casting completed.
2nd phase Waterproofing for main raft top preparation 10% completed.

Under Ground Raft Works:

1st phase Waterproofing for raft (above PCC) and retaining walls completed.
Raft Reinforcement for UG Pump room and Water Tank (WT) completed.
UG raft and vertical elements for WT and pump room casting completed.
External waterproofing for WT walls 20% completed.

Launched: 15th July 2024
Planned Handover: 30th March 2026

Progress:

4.32%

Stage:

Main Raft:

1st Phase Of Waterproofing For Main Raft (Above PCC) Completed.
1st Phase Waterproofing Protection Screed Casted.
Reinforcement For Main Raft Lift Pit 80% Completed.

Under Ground Raft Works:
Excavation, Levelling, Compaction For U/G Water Tank And Pump Room Raft Completed.
Solid Blockwork Shuttering For Raft And Retaining Walls Completed.
Dewatering System Installation Completed. Dewatering Process Ongoing.
1st Phase Waterproofing For Raft (Above PCC) And Retaining Walls 50% Completed.
Launched: 15th July 2024
Planned Handover: 30th March 2026

Progress:

3.00%

Stage:

Water Tank and Pump Room: Zone 1 Excavation Completed.

Under Ground Raft Works:

Excavation completed including lift pits/LV rooms to required levels.
Compaction testing completed.
3 layers road base compaction and testing completed.
Raft foundation PCC blinging concrete casting completed.
Lift pit/LV room Raft Shuttering Works completed.
Water Proofing Preliminarily Works completed.

Launched:

15th July 2024

Planned Handover:

30th March 2026