The Hub Residences by ZāZEN – Construction Update
Al Furjan
It is currently under construction and is planned for completion in January 2027 .
This project is registered under RERA project number 3419.
Timeline
| Progress: | 5.15% |
| Stage: | Excavation Works: · Main raft area – 85% completed.· Staircase & UG water tank – 100% completed.· UG pump room & sump pit – 80% completed. Dewatering Works: Road base & Compaction Works: Solid Block Works: PCC Works: Waterproofing & Reinforcement Works: |
| Construction Start: | July 2025 |
| Planned Completion: | January 2027 |
| Progress: | 2.86% |
| Stage: | Mobilization Works
Excavation Works
Dewatering Works
Roadbase Works
Solid Block Works
PCC Works
|
| Construction Start: | July 2025 |
| Planned Completion: | January 2027 |
| Progress: | 1.00% |
| Stage: | Mobilization Works:
Excavation Works:
Dewatering Works:
|
| Construction Start: | July 2025 |
| Planned Completion: | January 2027 |