ZāZEN IVY – Construction Update

Al Furjan

9.12%

It is currently under construction and due for completion in March 2026.

This project is registered under RERA project number 3109.

Timeline

Progress:

9.12%

Stage:

Main Raft:

Reinforcement for main raft, lift pit and substation completed.
Main Raft concrete casting completed.
2nd phase Waterproofing for main raft top preparation 10% completed.

Under Ground Raft Works:

1st phase Waterproofing for raft (above PCC) and retaining walls completed.
Raft Reinforcement for UG Pump room and Water Tank (WT) completed.
UG raft and vertical elements for WT and pump room casting completed.
External waterproofing for WT walls 20% completed.

Launched: 15th July 2024
Planned Handover: 30th March 2026

Progress:

4.32%

Stage:

Main Raft:

1st Phase Of Waterproofing For Main Raft (Above PCC) Completed.
1st Phase Waterproofing Protection Screed Casted.
Reinforcement For Main Raft Lift Pit 80% Completed.

Under Ground Raft Works:
Excavation, Levelling, Compaction For U/G Water Tank And Pump Room Raft Completed.
Solid Blockwork Shuttering For Raft And Retaining Walls Completed.
Dewatering System Installation Completed. Dewatering Process Ongoing.
1st Phase Waterproofing For Raft (Above PCC) And Retaining Walls 50% Completed.
Launched: 15th July 2024
Planned Handover: 30th March 2026

Progress:

3.00%

Stage:

Water Tank and Pump Room: Zone 1 Excavation Completed.

Under Ground Raft Works:

Excavation completed including lift pits/LV rooms to required levels.
Compaction testing completed.
3 layers road base compaction and testing completed.
Raft foundation PCC blinging concrete casting completed.
Lift pit/LV room Raft Shuttering Works completed.
Water Proofing Preliminarily Works completed.

Launched:

15th July 2024

Planned Handover:

30th March 2026