ZāZEN IVY – Construction Update

Al Furjan

3%

It is currently under construction and due for completion in March 2026.

This project is registered under RERA project number 3109.

Timeline

Progress:

3.00%

Stage:

Water Tank and Pump Room: Zone 1 Excavation Completed.

Under Ground Raft Works:

Excavation completed including lift pits/LV rooms to required levels.
Compaction testing completed.
3 layers road base compaction and testing completed.
Raft foundation PCC blinging concrete casting completed.
Lift pit/LV room Raft Shuttering Works completed.
Water Proofing Preliminarily Works completed.

Launched:

15th July 2024

Planned Handover:

30th March 2026