مستجدات الإنشاء – ذا هاب ريزيدن
CONSTRUCTION UPDATES
9.50%
THE HUB RESIDENCES BY ZāZEN
It is currently under construction and is planned for completion in January 2027 . This project is registered under RERA project number 3419.
VIEW PROJECT
DELIVERED
TIMELINE
The Hub Residences JOURNEY
Progress
9.50%
Stage
Excavation Works:
- Main raft area – 100% completed
- Staircase & UG water tank – 100% completed
- UG pump room & sump pit – 100% completed
Dewatering Works:
Dewatering – Under progress.
Road base & Compaction Works:
- Main raft foundation area – 80% completed
- Isolated footing – 90% completed
- UG Water tank & Pump room – 90% completed
Solid Block Works:
Solid Block works for main raft area – 100% completed
- PCC Works:
- PCC below Raft foundation – 85% completed
- PCC Below Isolated footing – 85% completed
Waterproofing & Reinforcement Works:
- Waterproofing membrane below Main Raft foundation – 70% completed
- Waterproofing membrane for Isolated footing – 75% completed
- Waterproofing membrane for UG tank & pump room – 100% completed
Reinforcement & Concrete Works:
- Steel reinforcement work for the Isolated footing & substation – 75% completed
- Steel reinforcement work for raft – 65% completed
- Steel reinforcement work for Neck column at Isolated footing – 80% completed
- Isolated footing concrete casting – 75% completed
- Neck column concrete casting at Isolated footing – 80% completed
Construction Start
July 2025
Planned Completion
January 2027
Excavation Works:
6.50%
Stage
Excavation Works:
Main raft area – 90% completed
UG pump room & sump pit – 90% completed
UG pump room & sump pit – 90% completed
Solid Block Works:
Solid Block works for main raft area – 75% completed
PCC Works:
PCC below Raft foundation – 70% completed
PCC Below Isolated footing – 85% completed
PCC Below Isolated footing – 85% completed
Waterproofing & Reinforcement Works:
Waterproofing membrane below Main Raft foundation – 55% completed
Waterproofing membrane for Isolated footing – 75% completed
Waterproofing membrane for Isolated footing – 75% completed
- PCC Works:
- PCC below Raft foundation – 85% completed
- PCC Below Isolated footing – 85% completed
Reinforcement & Concrete Works:
- Steel reinforcement work for the Isolated footing & substation – 75% completed
- Steel reinforcement work for raft – 30% completed
- Steel reinforcement work for Neck column at Isolated footing – 80% completed
- Isolated footing concrete casting – 75% completed
- Neck column concrete casting at Isolated footing – 80% completed
Construction Start
July 2025
Planned Completion
January 2027
Progress
5.15%
Progress
Excavation Works:
- Main raft area – 85% completed
- Staircase & UG water tank – 100% completed.
- UG pump room & sump pit – 80% completed.
Dewatering Works:
Dewatering – Under progress.
Road base & Compaction Works:
- Main raft foundation area – 80% completed
- Isolated footing – 85% completed
- UG staircase – 100% completed.
- UG Water tank & Pump room – 80% completed
Solid Block Works:
Solid Block works for main raft area – 75% completed
- PCC Works:
- PCC below Raft foundation – 75% completed
- PCC Below Isolated footing – 85% completed
Waterproofing & Reinforcement Works:
- Waterproofing membrane below Main Raft foundation – 50% completed
- Waterproofing membrane for Isolated footing – 75% completed
- Steel reinforcement work for the Isolated footing & substation – 50% completed.
Construction Start
July 2025
Planned Completion
January 2027

Progress
2.86%
Stage
Mobilization Works
- Site Office, 100% completed.
Excavation Works:
- Excavation for Lift pit, 100% completed.
- Excavation for Water tank & pump room, 50% completed.
- Compaction of Main Excavation Area, 50% completed.
Dewatering Works:
- Mobilization for Dewatering works, 100% completed.
- Dewatering, under progress.
Roadbase Works
- Compaction, Leveling and Laying of roadbase, 50% completed.
Solid Block Works
Substation and lift area, 50% completed.
- PCC Works:
- PCC work below the Raft foundation, 50% completed.
Construction Start
July 2025
Planned Completion
January 2027

Progress
1.00%
Stage
Mobilization Works
- Site Office, 75% completed.
- Sign Board Erection, 100% completed.
- Store & Labor rest room, 100% completed.
Excavation Works:
- Excavation for main area, 100% completed.
- Excavation for water tank & pump room, 50% completed.
Dewatering Works:
- Mobilization for De-watering works, 50% completed.
Construction Start
July 2025
Planned Completion
January 2027